When installed for bilge pumping or ballast duty, centrifuga

题目
单选题
When installed for bilge pumping or ballast duty, centrifugal pumps require a () to remove air from the suction pipe.
A

air chamber

B

head lank

C

primer

D

prime mover

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

With UMS, when the engine room is unwatched will control the main engine

A.the bridge officer on watch

B.the chief engineer

C.the duty engineer

D.the duty motorman


正确答案:A

第2题:

Permission is kindly ______ about 1000 tons of clean sea water ballast,as and when required for trimming purposes.

A.requested to pump out

B.requested pumping out

C.requesting to pump out

D.requesting pumping out


正确答案:A

第3题:

Accidental flooding of the engine room bilges by the bilge main is prevented by( ).

A.stop-check valves installed in the bilge suction manifolds

B.using a positive displacement reciprocating bilge pump

C.installing educators in all bilge rose boxes

D.installing a swing check before each bilge valve


正确答案:A
解析:bilge main:舱底水总管;stop-check valves:截止止回阀
译文:在舱底水吸入总管设立截止止回阀可以防止由舱底水总管引起的舱底水泛滥。

第4题:

Is this a ()(淡水) tank?

  • A、bilge water
  • B、ballast water
  • C、fresh water
  • D、sea water

正确答案:C

第5题:

Which statement is TRUE concerning the placard entitled Discharge of Oil Prohibited ________.

A.It is required on all vessels

B.It may be located in a conspicuous place in the wheelhouse

C.It may be located at the bilge and ballast pump control station

D.All of the above


正确答案:C

第6题:

explain bilge and ballast pumping through ejector ?


正确答案:Bilge and ballast pumping is usually carried out via ejector during the stripping process .ejector works on the principle of the venturing tube .the driving water creates a vacuum which is responsible in drawing out the remaining bilge or ballast in the tank .

第7题:

A vessel in ocean service that does not have an approved means of processing oily bilge slops or oily ballast must have ______.

A.a fixed piping system for ballast discharge to a reception facility

B.a discharge outlet for the ballast system on each side of the weather deck

C.one portable adapter for a shore connection to the ballast line

D.All of the above


正确答案:A

第8题:

When the ships is going to enter into the harbor

A.change from heavy fuel oil to diesel oil for main engine

B.pumping out bilge water

C.change sea chest form high level one to lower level one

D.test emergency generator


正确答案:A

第9题:

Aboard damaged vessels, the MOST important consideration is preserving ______.

A.bilge pumping capacity

B.reserve buoyancy

C.level attitude

D.Instability


正确答案:B
在一艘受损的船上,考虑最重要的是保存剩余浮力。

第10题:

It is a ()(压载水) tank.

  • A、bilge water
  • B、ballast water
  • C、fresh water
  • D、sea water

正确答案:B

更多相关问题