What is NOT a requirement of the reinspection for a tank bar

题目
单选题
What is NOT a requirement of the reinspection for a tank barge with a certificate of inspection valid for two years? ()
A

The reinspection will be made between the fourteenth and sixteenth months

B

The inspector shall examine all accessible parts of the vessels's hull

C

The inspector shall examine the vessel's machinery as well as equipment

D

The scope of the reinspection shall be the same as for the inspection for certification,but in less detail

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

What is NOT accepted as the required shipping papers on a manned and loaded tank barge? ______.

A.Bill of Lading

B.Manifest

C.Shipping document

D.Logbook entry


正确答案:D

第2题:

What is NOT a requirement for the preparation of used,gasoline-propelled cars if they are to be carried as ordinary cargo and not as hazardous cargo ________.

A.The engine must be run until it dies from lack of fuel

B.The fuel tank must be inerted with CO2

C.The ignition key may not be in the ignition

D.The vehicle must be inspected for fuel leaks


正确答案:B

第3题:

What is the reserve requirement?

A.The requirement for cash reserves.

B.The requirement for deposits in cash.

C.The percentage of a bank's deposits in the form. of cash reserves.

D.The requirement of a bank to deposit a percentage of money.


正确答案:C
解析:文章倒数第二段提到It is assumed that...This is the reserve requirement.采取的是现金的形式。

第4题:

What refers to the depth of a petroleum product in a tank ________.

A.Innage

B.Outage

C.Thievage

D.Ullage


正确答案:A

第5题:

What is NOT a requirement of cargo piping installed in tank vessels carrying grade D or E cargo ONLY ________.

A.The cargo piping system shall be fixed

B.Flanged joints shall be used for pipe sizes exceeding 2 inches in diameter

C.Piping through bunker spaces may be run through a pipe tunnel

D.Connections at bulkheads must be made so that the plating does not form part of a flanged joint


正确答案:A

第6题:

What will be accepted as the shipping papers for an unmanned tank barge but will not be accepted if the tank barge is manned? ______.

A.Bill of Lading

B.Logbook entry

C.Manifest

D.Shipping document


正确答案:B

第7题:

What is NOT a requirement for the safe and effective use of a crude oil washing system ________.

A.Strip all tanks and remove the bottom residue

B.Use an inert gas system while washing tanks

C.Use portable washing machines to reach areas obscured by structural members in the tanks

D.Debottom the tank used as the source for the tank cleaning machines


正确答案:C

第8题:

What is the reserve requirement?

A.The requirement of a bank to deposit a percentage of money

B.The requirement for deposits in cash

C.The percentage of a bank's deposits in the form. of cash reserves

D.The requirement for cash reserves


正确答案:A
解析:法定存款准备金(reserve requirement)要求商业银行必须按存款的一定比率在其央行账户存放款项。

第9题:

What is a requirement for remote manual shutdown stations for internal combustion engine driven cargo pumps on tank barges ________.

A.They must be conspicuously marked

B.They must be located at least 10 feet from the engine

C.There must be at least two such shutdown devices

D.The valve rods shall be fitted with stuffing boxes


正确答案:A

第10题:

You are planning to use a crude oil washing system.What precaution must be taken with the tank as the source for the washing machines ________.

A.It must be debottomed and the level lowered by at least one meter

B.The oil in the source tank must be sampled for compatibility

C.The source tank must have been crude oil washed at least once in the past 150 days

D.The inert gas system must lower the oxygen content to a maximum of 12% oxygen in the tank


正确答案:A