第1题:
The following individuals are responsible for determining the content of the Communications Management Plan.
A Project Sponsor
B Task Manager(s)
C Director of Communications
D Project Manager
第2题:
75 Input into the Communications Management Plan includes the following information from the stakeholder analysis:
A. Information needs
B. Information content
C. Frequency of distribution
D. Method of distribution
E. All of the above
第3题:
● Project Quality Management processes include all the activities of the (71) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.
(71)
A. project
B. project management team
C. performing organization
D. customer
第4题:
The inputs of developing project management plan do not include(72). A.project charter B.stakeholder management strategy C.project scope statement D.outputs from planning processes
第5题:
A. The communication management plan is contained in or is a subsidiary plan of, the project management plan.
B. The communication management plan can be formal or informal, highly detailed or broadly framed, and based on the needs of the project.
C. The communication manamgement plan organize and summarize the information gathered,and present the results of any analysis as comparedthe performance measurement baseline.
D. The communication management plan can include guidelines project status meetings,project team meetings,e-meetines,and e-mail
第6题:
73 The following individuals are responsible for determining the content of the Communications Management Plan.
A. Project Sponsor
B. Task Manager(s)
C. Director of Communications
D. Project Manager
第7题:
In the project management context()includes characteristics of unification,consolidation, articulation, and integrative actions that are crucial to project completion,successfully meeting customer and other stakeholder requirements, and managing expectations.
A.integration
B.scope
C.process
D.charter
该题的关键词为"unification、consolidation、articulation、integrativeactions",其语句结构为"(主语)includes(谓语)characteristics of unification,consolidation,articulation,andintegrativeactions",含义为"什么包括了统一、合并、沟通的特征以及集成活动",根据语句的含义容易识别为集成(或整体),对应的英文为Integration。
第8题:
Input into the Communications Management Plan includes the following information from the stakeholder analysis:
A Information needs
B Information content
C Frequency of distribution
D Method of distribution
E All of the above
第9题:
● The inputs of developing project management plan do not include (72).
(72)
A. project charter
B. stakeholder management strategy
C. project scope statement
D. outputs from planning processes
第10题:
Project Quality Management processes include all the activities of the (75) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.
A.performing organization
B.project management team
C.project
D.customer