单选题What document impressed Ms. Andersen?A The budget reportB The purchasing agreementC The launch programD The work schedule

题目
单选题
What document impressed Ms. Andersen?
A

The budget report

B

The purchasing agreement

C

The launch program

D

The work schedule

参考答案和解析
正确答案: A
解析:
第二封邮件第三句提到男士附上的文件让她印象深刻,而在第一封邮件第二段最后“I have attached a copy of the final deal with this email”提到他发送了采购协议,所以B项正确。
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

The Cost Performance Index is computed as:

A . budget cost of work performed divided by actual cost of work performed

B . budget cost of work performed minus actual cost of work performed

C . budget cost of work performed minus budget cost of work scheduled

D . budget cost of work scheduled divided by budget cost of work performed

E . actual cost of work scheduled divided by budget cost of work performed


正确答案:A

第2题:

In performing an impact analysis, the most effective tool to ensure all risks are identified on large projects is the:

A Work breakdown structure

B milestone review and schedule technique

C cost/schedule control system

D planning programming budget system

E program and evaluation review technique


正确答案:A

第3题:

Project trade-offs vary between

A . risk, cost and schedule.

B . direct cost, indirect cost, and resource availability

C . quality, schedule and time

D . cost, quality and schedule

E . contract terms, scope and budget


正确答案:D

 

第4题:

● Which of the following are types of status reports?

A document, variance, trend and exception

B cost, trend, schedule and acquisition

C cost, schedule, technical performance

D analysis, cost, performance and schedule

E All of the above.


正确答案:C

第5题:

114 The Cost Performance Index is computed as:

A. budget cost of work performed divided by actual cost of work performed

B. budget cost of work performed minus actual cost of work performed

C. budget cost of work performed minus budget cost of work scheduled

D. budget cost of work scheduled divided by budget cost of work performed

E. actual cost of work scheduled divided by budget cost of work performed


正确答案:A

第6题:

A negative cost variance and positive schedule variance means:

A The project is under budget and ahead of schedule

B The project is over budget and behind schedule

C The project is over budget and ahead of schedule

D The project will be overrun but ahead of schedule at completion


正确答案:C

第7题:

178 In performing an impact analysis, the most effective tool to ensure all risks are identified on large projects is the:

A. Work breakdown structure

B. milestone review and schedule technique

C. cost/schedule control system

D. planning programming budget system

E. program and evaluation review technique


正确答案:A

第8题:

The Work Breakdown Structure (WBS) is the basis for communicating:

A.Project scope, cost control, schedule, quality

B.Project objectives, dependencies, plan, cost control

C.Project scope, schedule, staffing, cost control

D.Project scope, quality, schedule, dependencies

E.Project budget, schedule, risk factors, work assignments.


正确答案:A
A

第9题:

96 A negative cost variance and positive schedule variance means:

A. The project is under budget and ahead of schedule

B. The project is over budget and behind schedule

C. The project is over budget and ahead of schedule

D. The project will be overrun but ahead of schedule at completion


正确答案:C

第10题:

● The Work Breakdown Structure (WBS) is the basis for communicating:

A Project scope, cost control, schedule, quality

B Project objectives, dependencies, plan, cost control

C Project scope, schedule, staffing, cost control

D Project scope, quality, schedule, dependencies

E Project budget, schedule, risk factors, work assignments.


正确答案:A