单选题During an internal IT organization planning session, it is decided that a new cluster node would  Enhance the performance of a distributed corporate application. Planning details have been assigned to the administrator. System outages are limited to on

题目
单选题
During an internal IT organization planning session, it is decided that a new cluster node would  Enhance the performance of a distributed corporate application. Planning details have been assigned to the administrator. System outages are limited to one weekend per month; therefore, availability will be a key issue in the planning process.  How much cluster downtime will need to be allocated for adding a new node?()
A

 None,everything can be done with the cluster active.

B

 Minimal downtime will be required to import the volume groups.

C

 Several hours are required for testing before final synchronization.

D

 Minimal downtime will be required to connect and test the serial network.

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

Which of the following would be considered reasonable network maintenance tasks?(Choose allthat apply.)()

  • A、Ensuring compliance with legal regulations and corporate policies
  • B、Troubleshooting problem reports
  • C、Planning for network expansion
  • D、Providing support to sales and marketing
  • E、Giving presentations to management
  • F、Monitoring and tuning network performance

正确答案:A,B,C,F

第2题:

A new administrator is performing fallover testing on a two-node cluster and is concerned that the cascading resource group belonging to Node ’A’ did not reintegrate properly after the cluster was restarted on Node ’A’. A stable cluster is reported by clstat,and clRGinfo reports the resource group online on Node ’B’.  What type of configuration would cause this type of behavior?()  

  • A、 The resource group DNP has been configured.
  • B、 The resource group option CWOF has been enabled.
  • C、 The resource group option Inactive Takeover is set.
  • D、 A resource group fallback timer has been configured.

正确答案:B

第3题:

Using the following information: Performance data from an existing system that a new system will replace; Performance estimates that anticipate future workloads; Micro-partitioning and logical partitioning implementations. Which of the following allows a technical sales representative to create a system design which can be imported into an HMC?()

  • A、IBMeConfig
  • B、IBM Performance Monitor
  • C、IBM Workload Estimator (WLE)
  • D、IBM System Planning Tool (SPT)

正确答案:D

第4题:

During a planning session, the customer indicates the need to provide high availability between a  Node attached to an IBM TotalStorage Enterprise Storage Server and a remote node attached to a IBM TotalStorage FAStT server with automatic fallover in the event of a disaster.  Which of the following HACMP options will provide this functionality?()  

  • A、 GeoRM
  • B、 HACMP/XD://PPRC
  • C、 HACMP/XD://GPFS
  • D、 HACMP/XD://HAGEO

正确答案:D

第5题:

A customer has 5 older POWER5 systems and they want to consolidate them onto a POWER6 system. What information is important to analyze when deciding how to design the new machine using the System Planning Tool?()

  • A、 vmstat and iostat data from the older machines 
  • B、 The number of CPUs that were installed in the original machines 
  • C、 Data from Workload Estimator (WLE) and IBM Performance Management (PM) 
  • D、 Performance data that is collected from the new system after it has been put into production

正确答案:C

第6题:

During Company.com planning session,Company.com presents the details of the current  Network design. The network design serves four separate company facilities, each on as separate subnet. As part of a disaster recovery plan, the customer is evaluating the use of HACMP. Specifically, the have reviewed IPAT via IP aliasing and are questioning the number of IP subnets required.  Given the customer’s current configuration,what is the recommended minimum number of IP subnets that would be required?()

  • A、 4
  • B、 5
  • C、 6
  • D、 8

正确答案:C

第7题:

During Company.com planning session, the LVM requirements for HACMP are provided. The administrator explains that there are five volume groups in the current production environment because filesystems constantly change due to the nature of the business. Maintenance outages are limited to one Saturday per month. There is some concern about the amount of time that will be required for outages once HACMP is installed.  With HACMP,what will be the simplest methods of managing LVM changes while minimizing required downtime.()  

  • A、 Make changes and allows Lazy Update to sync the changes later.
  • B、 Use the Cluster Single Point Of Control to manage LVM changes.
  • C、 Use exportvg on the primary node and improtvg on the second node.
  • D、 Set up a local NFS cross-mount, and use the local filesystem until the outage.

正确答案:B

第8题:

You are planning to connect your three branch offices to the corporate site via Frame Relay. The first branch office has been assigned the network 10.1.0.0/16, the second 10.2.0.0/16, the third 10.3.0.0/16, and the corporate headquarters uses 10.0.0.0/16. You would like to summarize all branch and corporate networks into a single route at the corporate site. Which network address and subnet mask should you choose?()  

  • A、 10.0.0.0/24
  • B、 10.0.0.0/16
  • C、 10.0.0.0/14
  • D、 10.0.0.0/15

正确答案:C

第9题:

During a planning session, it is determined that a three node cluster (Node ’A’, Node ’B’, and Node ’C’) will meet the customer’s application needs. Node ’B’ will be a hot-standby fallover node for both Node ’A’ and Node ’C’ resource groups.  A serial network for this cluster will require which connections?()  

  • A、 A single serial network between Node ’A’ and Node ’B’ and Node ’C’
  • B、 A point-to-point link between Node ’A’ and Node ’C’,and Node ’B’ and Node ’C’
  • C、 A serial network between Node ’A’ and Node ’C’,and a serial network between Node ’B’ and Node ’C’
  • D、 A point-to-point link between Node ’A’ and Node ’B’ Node ’B’ and Node ’C’ and Node ’A’ ad Node ’C’

正确答案:D

第10题:

During an internal IT organization planning session, it is decided that a new cluster node would  Enhance the performance of a distributed corporate application. Planning details have been assigned to the administrator. System outages are limited to one weekend per month; therefore, availability will be a key issue in the planning process.  How much cluster downtime will need to be allocated for adding a new node?()  

  • A、 None,everything can be done with the cluster active.
  • B、 Minimal downtime will be required to import the volume groups.
  • C、 Several hours are required for testing before final synchronization.
  • D、 Minimal downtime will be required to connect and test the serial network.

正确答案:A