The way a project manager sends and receives information depends upon:
A How others relate to the project manager
B The project manager's level in the organizational hierarchy
C the size and nature of the project
D the project manager's salary and age
E the number of projects going on at one time in the company
第2题:
108 The way a project manager sends and receives information depends upon:
A. How others relate to the project manager
B. The project manager's level in the organizational hierarchy
C. the size and nature of the project
D. the project manager's salary and age
E. the number of projects going on at one time in the company
第3题:
In the project environment, the individual ultimately responsible for quality control is:
A . The line workers who must strive "to do things right the first time" to avoid quality problems.
B . the company's quality control manager who must work with the project members to ensure the quality control program is effective.
C . The head of the production department who retains ultimate quality control responsibility for all the company's projects.
D . The project manager who has ultimate responsibility for the entire project.
E . the customer who must ensure that he is receiving a quality product from the vendor.
第4题:
In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project‘s communication. According to Metcalfe‘s Law, a project with 10 stakeholders has()potential communication channels.
A.10
B.45
C.50
D.100
第5题:
189 Ouchi's Theory Z relates more to _____ whereas Theory X / Theory Y relates to _____ .
A. Project managers; team members
B. Company management philosophy in treating employees; the average worker
C. Project sponsors; project managers
D. The functional team; project sponsors
E. Recruitment policy; wage and salary administration
第6题:
It is useful to conduct project risk assessment according to the project's
A charter
B statement of work
C Work Breakdown structure
D network
E budget
第7题:
41 In the project environment, the individual ultimately responsible for quality control is:
A. The line workers who must strive "to do things right the first time" to avoid quality problems. B. the company's quality control manager who must work with the project members to ensure the quality control program is effective.
C. The head of the production department who retains ultimate quality control responsibility for all the company's projects.
D. The project manager who has ultimate responsibility for the entire project.
E.the customer who must ensure that he is receiving a quality product from the vendor
第8题:
Ouchi's Theory Z relates more to _____ whereas Theory X / Theory Y relates to _____ .
A . Project managers; team members
B . Company management philosophy in treating employees; the average worker
C . Project sponsors; project managers
D . The functional team; project sponsors
E . Recruitment policy; wage and salary administration
第9题:
66 A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:
A. Change the scope baseline
B. Prepare a variance report
C. Call a meeting of the configuration control board
D. Change the project's objectives
E. Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
第10题:
● A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:
A Change the scope baseline
B Prepare a variance report
C Call a meeting of the configuration control board
D Change the project's objectives
E Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline