According to Aleem Walji, the company’s first project is to

题目
单选题
According to Aleem Walji, the company’s first project is to _____.
A

set up a new system to warn people of infectious diseases

B

find out where infectious diseases develop

C

identify the causes of infectious diseases

D

cure patients of infectious diseases

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

The way a project manager sends and receives information depends upon:

A How others relate to the project manager

B The project manager's level in the organizational hierarchy

C the size and nature of the project

D the project manager's salary and age

E the number of projects going on at one time in the company


正确答案:A

第2题:

108 The way a project manager sends and receives information depends upon:

A. How others relate to the project manager

B. The project manager's level in the organizational hierarchy

C. the size and nature of the project

D. the project manager's salary and age

E. the number of projects going on at one time in the company


正确答案:A

第3题:

In the project environment, the individual ultimately responsible for quality control is:

A . The line workers who must strive "to do things right the first time" to avoid quality problems.

B . the company's quality control manager who must work with the project members to ensure the quality control program is effective.

C . The head of the production department who retains ultimate quality control responsibility for all the company's projects.

D . The project manager who has ultimate responsibility for the entire project.

E . the customer who must ensure that he is receiving a quality product from the vendor.


正确答案:D

第4题:

In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project‘s communication. According to Metcalfe‘s Law, a project with 10 stakeholders has()potential communication channels.

A.10

B.45

C.50

D.100


参考答案:B

第5题:

189 Ouchi's Theory Z relates more to _____ whereas Theory X / Theory Y relates to _____ .

A. Project managers; team members

B. Company management philosophy in treating employees; the average worker

C. Project sponsors; project managers

D. The functional team; project sponsors

E. Recruitment policy; wage and salary administration


正确答案:B

第6题:

It is useful to conduct project risk assessment according to the project's

A charter

B statement of work

C Work Breakdown structure

D network

E budget


正确答案:C

第7题:

41 In the project environment, the individual ultimately responsible for quality control is:

A. The line workers who must strive "to do things right the first time" to avoid quality problems. B. the company's quality control manager who must work with the project members to ensure the quality control program is effective.

C. The head of the production department who retains ultimate quality control responsibility for all the company's projects.

D. The project manager who has ultimate responsibility for the entire project.

E.the customer who must ensure that he is receiving a quality product from the vendor


正确答案:D

第8题:

Ouchi's Theory Z relates more to _____ whereas Theory X / Theory Y relates to _____ .

A . Project managers; team members

B . Company management philosophy in treating employees; the average worker

C . Project sponsors; project managers

D . The functional team; project sponsors

E . Recruitment policy; wage and salary administration


正确答案:B

第9题:

66 A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:

A. Change the scope baseline

B. Prepare a variance report

C. Call a meeting of the configuration control board

D. Change the project's objectives

E. Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline


正确答案:E

第10题:

● A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:

A Change the scope baseline

B Prepare a variance report

C Call a meeting of the configuration control board

D Change the project's objectives

E Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline


正确答案:E

更多相关问题