第1题:
Resource leveling _____.
A.Allocates resources to activities to find shortest schedule within fixed resource limits.
B.Smoothes out resource requirements by rescheduling activities within their float time.
C.Smooths out resource requirements by substituting activities with unassigned resources.
D.Attempts to reduce resource requirements within a constraint on project duration
E.B or D
第2题:
111 It is useful to conduct project risk assessment according to the project's
A. charter
B. statement of work
C. Work Breakdown structure
D. network
E. budget
第3题:
A program is characterized as:
A.a grouping or related tasks lasting one year or less.
B.a unique undertaking having a definite time period.
C.a grouping of similar projects having no definite end that supports the product(s) from cradle to grave.
D.a project with a cost over $ million.
E.None of the above.
第4题:
● A project is defined as:
A a coordinated undertaking of interrelated activities directed toward a specific goal that has a finite period of performance.
B a large, complex undertaking with many objectives, multiple sources of funding, and a not discernible end point.
C an undertaking of interrelated activities directed toward a specific goal that can be accomplished in less than one year.
D a group of activities headed by a project manager who has cradle-to-grave cycle responsibility for the end product.
E All of the above.
第5题:
A. completing
B. complete
C. to complete
D. completed
第6题:
It is useful to conduct project risk assessment according to the project's
A charter
B statement of work
C Work Breakdown structure
D network
E budget
第7题:
200 A program is characterized as:
A. a grouping or related tasks lasting one year or less.
B. a unique undertaking having a definite time period.
C. a grouping of similar projects having no definite end that supports the product(s) from cradle to grave. D. a project with a cost over $1 million.
E. None of the above
第8题:
A project is defined as:
A.a coordinated undertaking of interrelated activities directed toward a specific goal that has a finite period of performance.
B.a large, complex undertaking with many objectives, multiple sources of funding, and a not discernible end point.
C.an undertaking of interrelated activities directed toward a specific goal that can be accomplished in less than one year.
D.a group of activities headed by a project manager who has cradle-to-grave cycle responsibility for the end product.
E.All of the above.
第9题:
A.This process assigns cost estimates to project activities including risks and contingency plans.
B.The cost baseline will be used to measure variances and future project performance.
C.This process assigns cost estimates for expected future period operating costs.
D.The cost baseline is the expected cost for the project.
第10题:
● Resource leveling _____.
A Allocates resources to activities to find shortest schedule within fixed resource limits.
B Smoothes out resource requirements by rescheduling activities within their float time.
C Smooths out resource requirements by substituting activities with unassigned resources.
D Attempts to reduce resource requirements within a constraint on project duration
E B or D