A project is a[temporary](请作答此空)of unique,complex,and connected activities having one goal or purpose and that must be completed by a specific time,within budget,and according to( ).Project managemen

题目
A project is a[temporary](请作答此空)of unique,complex,and connected activities having one goal or purpose and that must be completed by a specific time,within budget,and according to( ).Project management is the process of scoping,planning,staffing,organizing,directing,and controlling the development of a(n)( )system at a minimum cost within a specified time frame.For any systems development project,effective project management is necessary to ensure that the project meets the( ),is developed within an acceptable budget,and fulfills customer expectations and specifications,Project management is a process that starts at the beginning of a project,extends through a project,and doesn't culminate until the project is completed.The prerequisite for good project management is a well-defined system development process.Process management is an ongoing activity that documents,manages the use of,and improves an organization s chosen methodology(the“process”)for system development,Process management is concerned with the activities,deliverables,and quality standards to be applied to( )project(s).

A.task
B.work
C.sequence
D.activity
参考答案和解析
答案:C
解析:
表示序列的意思。
附(参考翻译):一个项目是一个独特的、复杂的、相互关联的活动的[临时]序列,有一个目标或目的,必须在特定的时间、预算内和根据规范完成。项目管理是一个范围界定、计划、人员配置、组织、指导和控制可接受系统开发的过程,在规定的时间内以最低的成本进行。对于任何系统开发项目,有效的项目管理都是必要的,以确保项目在截止日期前完成,在可接受的预算内开发,并满足客户的期望和规范,项目管理是从项目开始时开始的过程,延伸到一个项目中,直到项目完成才达到顶点。良好的项目管理的先决条件是定义良好的系统开发过程。过程管理是一项持续的活动,它记录、管理和改进组织为系统开发所选择的方法(“过程”),过程管理涉及应用于所有项目的活动、可交付成果和质量标准。
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

Resource leveling _____.

A.Allocates resources to activities to find shortest schedule within fixed resource limits.

B.Smoothes out resource requirements by rescheduling activities within their float time.

C.Smooths out resource requirements by substituting activities with unassigned resources.

D.Attempts to reduce resource requirements within a constraint on project duration

E.B or D


正确答案:E
E

第2题:

111 It is useful to conduct project risk assessment according to the project's

A. charter

B. statement of work

C. Work Breakdown structure

D. network

E. budget


正确答案:C

第3题:

A program is characterized as:

A.a grouping or related tasks lasting one year or less.

B.a unique undertaking having a definite time period.

C.a grouping of similar projects having no definite end that supports the product(s) from cradle to grave.

D.a project with a cost over $ million.

E.None of the above.


正确答案:C
C

第4题:

● A project is defined as:

A a coordinated undertaking of interrelated activities directed toward a specific goal that has a finite period of performance.

B a large, complex undertaking with many objectives, multiple sources of funding, and a not discernible end point.

C an undertaking of interrelated activities directed toward a specific goal that can be accomplished in less than one year.

D a group of activities headed by a project manager who has cradle-to-grave cycle responsibility for the end product.

E All of the above.


正确答案:A

第5题:

We must ____ the project within 10 days.

A. completing

B. complete

C. to complete

D. completed


正确答案:B

第6题:

It is useful to conduct project risk assessment according to the project's

A charter

B statement of work

C Work Breakdown structure

D network

E budget


正确答案:C

第7题:

200 A program is characterized as:

A. a grouping or related tasks lasting one year or less.

B. a unique undertaking having a definite time period.

C. a grouping of similar projects having no definite end that supports the product(s) from cradle to grave. D. a project with a cost over $1 million.

E. None of the above


正确答案:C

第8题:

A project is defined as:

A.a coordinated undertaking of interrelated activities directed toward a specific goal that has a finite period of performance.

B.a large, complex undertaking with many objectives, multiple sources of funding, and a not discernible end point.

C.an undertaking of interrelated activities directed toward a specific goal that can be accomplished in less than one year.

D.a group of activities headed by a project manager who has cradle-to-grave cycle responsibility for the end product.

E.All of the above.


正确答案:A
A

第9题:

You are working on the cost budget for one project. Which of the following is true()

A.This process assigns cost estimates to project activities including risks and contingency plans.

B.The cost baseline will be used to measure variances and future project performance.

C.This process assigns cost estimates for expected future period operating costs.

D.The cost baseline is the expected cost for the project.


参考答案:B

第10题:

● Resource leveling _____.

A Allocates resources to activities to find shortest schedule within fixed resource limits.

B Smoothes out resource requirements by rescheduling activities within their float time.

C Smooths out resource requirements by substituting activities with unassigned resources.

D Attempts to reduce resource requirements within a constraint on project duration

E B or D


正确答案:E

更多相关问题