单选题A customer has ten RS/6000 Model M80, two pSeries 690 Model 681, five POWER5 510 and two POWER6 560 machines installed and running commercial applications. They want to do a server consolidation study in order to replace the existing systems with POWER

题目
单选题
A customer has ten RS/6000 Model M80, two pSeries 690 Model 681, five POWER5 510 and two POWER6 560 machines installed and running commercial applications. They want to do a server consolidation study in order to replace the existing systems with POWER7 systems. What performance metric is recommended when evaluating the replacement system?()
A

IBM CPW

B

IBM rPerf

C

SPECint_rate2006

D

IDEAS International RPE2

参考答案和解析
正确答案: A
解析: 暂无解析
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

A customer has a mixed environment of AIX on POWER4 and POWER5, and x86 based systems running a supported distribution of Linux. There is a total of 7 partitions and three standalone x86 servers. The customer wants to consolidate their applications using a single 4-core POWER6 server.  What is the minimum PowerVM edition that supports the customer requirement?()

  • A、 PowerVM Lx86
  • B、 PowerVM Express Edition
  • C、 PowerVM Standard Edition
  • D、 PowerVM Enterprise Edition

正确答案:C

第2题:

A customer has ten RS/6000 Model M80, two pSeries 690 Model 681, five POWER5 510 and two POWER6 560 machines installed and running commercial applications. They want to do a server consolidation study in order to replace the existing systems with POWER7 systems. What performance metric is recommended when evaluating the replacement system?()

  • A、IBM CPW
  • B、IBM rPerf
  • C、SPECint_rate2006
  • D、IDEAS International RPE2

正确答案:B

第3题:

AcustomerhastenRS/6000ModelM80,twopSeries690Model681,fivePOWER5510andtwoPOWER6560machinesinstalledandrunningcommercialapplications.TheywanttodoaserverconsolidationstudyinordertoreplacetheexistingsystemswithPOWER7systems.Whatperformancemetricisrecommendedwhenevaluatingthereplacementsystem?()

A.IBMCPW

B.IBMrPerf

C.SPECint_rate2006

D.IDEASInternationalRPE2


参考答案:B

第4题:

A customer has a key application running in a logical partition on a POWER5 system. The customer wants the ability to run the application with minimal down time using Live Partition Mobility.  Which of the following is the minimum PowerVM edition and hardware configuration that will support the customer requirement?()

  • A、 PowerVM Standard Edition on POWER6 hardware
  • B、 PowerVM Standard Edition with POWER5 hardware 
  • C、 PowerVM Enterprise Edition with POWER6 hardware
  • D、 PowerVM Enterprise Edition with POWER5 hardware

正确答案:C

第5题:

A customer has 5 older POWER5 systems and they want to consolidate them onto a POWER6 system. What information is important to analyze when deciding how to design the new machine using the System Planning Tool?()

  • A、 vmstat and iostat data from the older machines 
  • B、 The number of CPUs that were installed in the original machines 
  • C、 Data from Workload Estimator (WLE) and IBM Performance Management (PM) 
  • D、 Performance data that is collected from the new system after it has been put into production

正确答案:C

第6题:

The systems administrator of a large manufacturer has POWER5 and POWER6 servers, each with LPARs running AIX 6.1.  They are running several workloads including SAP, DNS, Oracle, DB2 and WebSphere Application Server, and plan to consolidate onto one POWER7 server.   How can the system administrator determine how much benefit Active Memory Expansion (AME) could provide for the consolidated system?()

  • A、Run amepat now on all of the existing LPARs.
  • B、Run amepat after consolidation on all LPARs.
  • C、Run amepat now on all existing LPARs running on the POWER6 servers.
  • D、Run amepat now on all existing LPARs running database applications.

正确答案:A

第7题:

An existing IBM customer has a few pSeries servers running DB2 on AIX in their environment.  The DB2 application contains the database for an order entry application.  An xSeries SQL database server replicating from DB2 is added for off-line analysis purposes.  The customer wants to know if consolidating the storage and centralized backup is possible. What are the options available to accomplish this?()

  • A、pSeries and xSeries use different file systems. Consolidating Storage and backup is not achievable.
  • B、Consolidation is possible by connecting pSeries local storage to the xSeries SQL server using the IXA adapter.
  • C、Storage consolidation can be achieved by connecting the pSeries and xSeries servers to a common DS4000 storage server.
  • D、Storage consolidation is only achievable when raw file systems are used by the databases and both servers run the same Linux file system (e.g., EXT3 or Reiser).

正确答案:C

第8题:

A customer has many RS/6000s and POWER4 systems running different AIX applications.  What should the customer do to best position themselves for the migration to POWER5?()

  • A、Upgrade OS to AIX 5.2.
  • B、Implement Micro-Partitioning.
  • C、Upgrade HMC to support POWER5.
  • D、Install Partition Load Manager.

正确答案:A

第9题:

A customer plans to consolidate several systems onto POWER7. Their immediate requirement is to have a single Power 770, and they will buy a second Power 770 at a later stage. They want to keep their existing three POWER5 570s and three POWER6 520s which are all managed by an HMC (7310-CR3). Which of these statements is true and would minimize the cost?()

  • A、All the machines can be connected to the existing HMC, as long as it is updated to code level 7.7.1 or later
  • B、The Power 770 requires an HMC (7042-CR5 or later), so they must buy one. All of the systems can be managed by this new HMC
  • C、They should buy a new HMC for the Power 770 system, and leave the POWER5 and POWER6 based  systems connected to the existing one
  • D、The Power 770 requires an HMC, so they should connect the Power 770 to the HMC and convert the POWER5 and POWER6 based servers to IVM

正确答案:A

第10题:

A customer is buying 10 new Power 720 servers and will integrate them into their existing data center which also has two Power 595s and five Power 750s, taking the total number of systems to 17. All currently installed systems are managed by a single HMC.All the machines will have dual VIO Servers for redundancy, and 10 client LPARs. How can they manage the new machines for the least cost?()

  • A、Purchase a second HMC and use this to manage the new servers.
  • B、Connect all of the new servers to the existing private HMC network.
  • C、Configure a second private network on their existing HMC for the new servers.
  • D、Connect 9 of the new servers to the existing HMC and use Integrated Virtualization Manager on the 10th.

正确答案:B