单选题The customer has both a Windows SAN and a separate UNIX SAN. Each of these is managed bya different group. The UNIX group has a need for more resources and no available funding. Whatis the first question the storage specialist should ask?()A What is th

题目
单选题
The customer has both a Windows SAN and a separate UNIX SAN. Each of these is managed bya different group. The UNIX group has a need for more resources and no available funding. Whatis the first question the storage specialist should ask?()
A

What is the SAN topology? 

B

Which vendor's storage product do you use? 

C

Are there additional storage resources available in the Windows SAN? 

D

Are there additional switch ports available in both the Windows and UNIX SANs?

参考答案和解析
正确答案: B
解析: 暂无解析
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

A customer’s SAN environment has undergone significant growth over the past two years. They have also suffered a high turnover rate with administrative personnel. The customer has asked a storage specialist for help in documenting and understanding their changing SAN environment. The ability to make configuration changes to devices would be a plus.  Which tool should the storage specialist suggest()

  • A、Tivoli Storage Productivity Center Fabric Manager
  • B、Tivoli Storage Productivity Center Basic Edition
  • C、IBM TivoliNetView
  • D、Disk Magic

正确答案:B

第2题:

The customer has both AIX and Windows hosts and is complaining that their storage infrastructureis complex and distributed. They need to simplify backup and restore operations. What productshould the storage specialist be prepared to discuss with them?()

  • A、Softek 
  • B、Tivoli Storage Manager FastBack 
  • C、Tivoli Storage Manager 
  • D、Tivoli Storage Productivity Center for Replication

正确答案:B

第3题:

A customer is planning to upgrade two VMware ESX servers from 3.5 to 4.1 after recently installing a new XIV Storage System. Each server has 4 HBAs connected to redundant fabrics for a total of 4 paths per server to storage. The customer wants to increase the throughput available to the ESX servers.What configuration setting does the storage specialist need to highlight?()

A. increase the buffer credits on the HBAs

B. increase the number of device logins on the ESX servers

C. additional paths will be required between the servers and storage

D. multipath option on the ESX servers should be changed to round-robin


参考答案:D

第4题:

A customer has a combination of fifteen Windows file servers with direct attached storage and three Power Systems with AIX database servers SAN attached to a DS4700.  They would like to upgrade and plan for 40 TB capacity.  The customer needs to move to a more scalable storage system to include all servers.Which of the following would be most appropriate to ask first?()

  • A、What are the plans for Disaster Recovery? 
  • B、What are the plans for data migration? 
  • C、Would iSCSI meet your needs? 
  • D、How much space is available in the current storage systems?

正确答案:B

第5题:

A customer is interested in purchasing a new IBM System Storage DS8000 solution to consolidateolder ESS and F20 storage systems. What should be done first, prior to final proposaldevelopment?()

  • A、perform a Disk Magic study 
  • B、review eConfig with a technical specialist 
  • C、confirm that the customer has enough ports available in the SAN infrastructure 
  • D、submit configuration to IBM System Storage Interoperability Center for validation

正确答案:A

第6题:

The customer has both a Windows SAN and a separate UNIX SAN. Each of these is managed bya different group. The UNIX group has a need for more resources and no available funding. Whatis the first question the storage specialist should ask?()

  • A、What is the SAN topology? 
  • B、Which vendor's storage product do you use? 
  • C、Are there additional storage resources available in the Windows SAN? 
  • D、Are there additional switch ports available in both the Windows and UNIX SANs?

正确答案:C

第7题:

A financial industry customer will consolidate their Intel-based servers to a p5-550 running AIX, and needs experienced technical services.  What information should the account executive provide to the customer to assure them that the technical specialist has the required experience?()

  • A、The technical specialist has supported multiple Cluster 1350 environments. References will be provided.
  • B、The technical specialist is Linux-certified by two industry groups. Certificate copies will be provided.
  • C、The technical specialist has worked on multiple UNIX consolidation projects.  References will be provided.
  • D、The technical specialist has worked on Linux consolidation efforts.  References will be provided.

正确答案:C

第8题:

A customer SAN environment has undergone significant growth over the past two years. They havealso suffered a high turnover rate with administrative personnel. The customer has asked a storage specialist for help in documenting and understanding their changing SAN environment. The ability to make configuration changes to devices would be a plus.    Which tool should the storage specialist suggest()

  • A、Visio
  • B、TPC Basic Edition
  • C、IBM Tivoli NetView
  • D、Fabric Manager

正确答案:B

第9题:

A customer is planning to upgrade two VMware ESX servers from 3.5 to 4.1 after recently installing a new XIV Storage System. Each server has 4 HBAs connected to redundant fabrics for a total of 4 paths per server to storage. The customer wants to increase the throughput available to the ESX servers. What configuration setting does the storage specialist need to highlight?()

  • A、increase the buffer credits on the HBAs
  • B、increase the number of device logins on the ESX servers
  • C、additional paths will be required between the servers and storage
  • D、multipath option on the ESX servers should be changed to round-robin

正确答案:D

第10题:

A storage specialist is proposing a solution consisting of an IBM System Storage TS3200 TapeLibrary and a SAN Volume Controller, both of which are being added to a customer’s existing SANenvironment for the first time. Which of the following should be completed before the proposal ispresented to the customer?()

  • A、TDA
  • B、Capacity Magic
  • C、business case review
  • D、SAN configuration review

正确答案:A

更多相关问题