Establishing a project management timetable involves listing milestones,activities,and()with intended start and finish dates,of which the scheduling of employees may be an element
A.relationships
B.resources
C.stakeholders
D.deliverables
第1题:
Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.
A.Project
B.project management team
C.performingorganization
D.customer
该题的关键词为"determine quality policies,objectives and responsibilities",其语句结构为"Project Quality Management processes(主语)include(谓语)all the activities of the (宾语)that determine quality policies,objectives and responsibilities(定语从句)",含义为"项目质量管理过程包括决定质量政策、质量目标以及质量责任的什么的所有活动",根据项目质量管理知识,只有组织才可以决定项目的质量政策,因而此处选择选项C。
第2题:
Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to(75) progress.
A.analyze
B.track
C.level
D.extend
第3题:
Free float is the amount of time that an activity may be delayed with out affecting the _____.
A.Early start of the succeeding activities.
B.Late start of the succeeding activities.
C.Project finish.
D.Cost of the project.
E.None of the above.
第4题:
A__(74)__is a type of bar chart that illustrates a project schedul
A.It illustrates the start and finish dates of the terminal elements and summary elements of a project.
B.Gantt chart
C.project histogram
D.milestone chart
E.project flowchart
第5题:
A()is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project.
A.gantt chart
B.project histogram
C.milestone chart
D.project flowchart
第6题:
● Free float is the amount of time that an activity may be delayed with out affecting the _____.
A Early start of the succeeding activities.
B Late start of the succeeding activities.
C Project finish.
D Cost of the project.
E None of the above.
第7题:
●Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to (75) progress.
(75)
A. analyze
B. track
C. level
D. extend
第8题:
Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.
A.Benchmarking
B.Quality metric
C.Quality checklist
D.Brainstornung
第9题:
In project management,a ( ) is a list of a project’s milestones,activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource allocation,budget and duration, linked by dependencies and scheduled events.
A.schedule
B.WBS
C.SOW
D.charter
第10题:
In project management , a (1) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (2) ,budget and duration, linked by dependencies and scheduled events.
A.schedule
B.activity
C.plan
D.contractor@@@SXB@@@A.finding
B.balance
C.allocation
D.distribution