The(75)process analyzes the effect of risk events and assigns a numerical rating to those

题目

The(75)process analyzes the effect of risk events and assigns a numerical rating to those risks.

A.Risk Identification

B.Quantitative Risk Analysis

C.Qualitative Risk Analysis

D.Risk Monitoring and Control

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

Screening of risk events for potential risk is known as _____ .

A problem structuring.

B risk identification

C risk quantification

D risk modeling

E risk mitigation


正确答案:B

第2题:

Total project risk can be defined as:

A the sum of the probabilities of project risks events times the sum of consequences of those risks

B the sum of the products of each project risk event times its consequences

C the sum of the consequences of all project risk events

D the sum of the probabilities of all project risk events

E 1 - the sum of the probabilities of all project risk events.


正确答案:B

第3题:

● The (75) process analyzes the effect of risk events and assigns a numerical rating to those risks.

A.Risk Identification

B.Quantitative Risk Analysis

C.Qualitative Risk Analysis

.Risk Monitoring and Control


正确答案:B

第4题:

170 Project Risk _____ .

A. should not be calculated for small projects.

B. is the probability of each risk event minus the sum of the consequences of potential risk events.

C. is the cumulative effect of uncertain occurrences which will adversely affect project objectives.

D. cannot be quantified for first time projects.

E. B or D


正确答案:C

第5题:

144 Risk event probability is defined as:

A. the total number of possible events divided into the expectations or frequency of the risk event

B. the number of times the risk event may occur

C. the fraction of the total project tasks which may be affected by the risk event

D. the total number of possible events divided into the consequences of the risk event.

E. A and B


正确答案:A

第6题:

Risk event probability is defined as:

A the total number of possible events divided into the expectations or frequency of the risk event

B the number of times the risk event may occur

C the fraction of the total project tasks which may be affected by the risk event

D the total number of possible events divided into the consequences of the risk event.

E A and B


正确答案:A

第7题:

15 Total project risk can be defined as:

A. the sum of the probabilities of project risks events times the sum of consequences of those risks

B. the sum of the products of each project risk event times its consequences

C. the sum of the consequences of all project risk events

D. the sum of the probabilities of all project risk events

E. 1 - the sum of the probabilities of all project risk events


正确答案:B

第8题:

Project Risk _____ .

A should not be calculated for small projects.

B is the probability of each risk event minus the sum of the consequences of potential risk events.

C is the cumulative effect of uncertain occurrences which will adversely affect project objectives.

D cannot be quantified for first time projects.

E B or D


正确答案:C

第9题:

113 Screening of risk events for potential risk is known as _____ .

A. problem structuring.

B. risk identification

C. risk quantification

D. risk modeling

E. risk mitigation


正确答案:B

第10题:

You are working on the cost budget for one project. Which of the following is true()

A.This process assigns cost estimates to project activities including risks and contingency plans.

B.The cost baseline will be used to measure variances and future project performance.

C.This process assigns cost estimates for expected future period operating costs.

D.The cost baseline is the expected cost for the project.


参考答案:B

更多相关问题