is one of the quality planning outputs.
A.Scope base line
B.Cost of quality
C.Product specification
D.Quality checklist
第1题:
123 Which of the following constitute Juran's "quality trilogy":
A. planning, inspection, control.
B. planning, improvement, control.
C. planning, organization, control.
D. product, price, customer.
E. design, build, deliver.
第2题:
3 Project tradeoffs are usually made by comparing _____ and constraints.
A. Time, cost, and quality
B. Time, risk, and quality
C. Risk, quality, and manpower availability
D. Cost, quality, and technical performance
E. Cost, quality, and risk
第3题:
Project tradeoffs are usually made by comparing _____ and constraints.
ATime, cost, and quality
BTime, risk, and quality
CRisk, quality, and manpower availability
DCost, quality, and technical performance
ECost, quality, and risk
第4题:
YouhaveaserverthatrunsWindowsServer2008ServicePack2(SP2).YouplantoinstallExchangeServer2010ontheserver.YouneedtoinstalltheExchangeServer2010prerequisitesfortheMailbox,ClientAccess,andHubTransportserverroles.Whatshouldyoudoontheserver()?
A.¡¤InstallMicrosoft.NETFramework3.5ServicePack1(SP1InstallWindowsManagementFrameworkrunServerManagerCmd.exeIPExchange-Typical.xml
B.¡¤InstallMicrosoft.NETFramework3.5ServicePack1(SP1InstallWindowsRemoteManagement(winRM)2.0RunServerManagerCmd.exeIPExchange-Base.xml
C.¡¤InstallWindowsManagementFrameworkInstallMessageQueuingInstalltheWebServerrole
D.¡¤InstallWindowsManagementFrameworInstalltheWebServerroleInstalltheRPCoverHTTPproxycomponent
第5题:
● Project tradeoffs are usually made by comparing _____ and constraints.
A Time, cost, and quality
B Time, risk, and quality
C Risk, quality, and manpower availability
D Cost, quality, and technical performance
E Cost, quality, and risk
第6题:
5 Which of the following constitute Juran's "quality trilogy":
A. planning, inspection, control.
B. planning, improvement, control.
C. planning, organization, control.
D. product, price, customer.
E. design, build, deliver.
第7题:
85 Project tradeoffs are usually made by comparing _____ and constraints.
A. Time, cost, and quality
B. Time, risk, and quality
C. Risk, quality, and manpower availability
D. Cost, quality, and technical performance
E. Cost, quality, and risk
第8题:
Which of the following constitute Juran's "quality trilogy":
A . planning, inspection, control.
B . planning, improvement, control.
C . planning, organization, control.
D . product, price, customer.
E . design, build, deliver.
第9题:
[A] spending
[B] planning
[C] financing
[D] saving
第10题: