In project management , a (1) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (2) ,budget and duration, linked by dependencies and scheduled events.
A.schedule
B.activity
C.plan
D.contractor@@@SXB@@@A.finding
B.balance
C.allocation
D.distribution
第1题:
Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.
A.Project
B.project management team
C.performingorganization
D.customer
该题的关键词为"determine quality policies,objectives and responsibilities",其语句结构为"Project Quality Management processes(主语)include(谓语)all the activities of the (宾语)that determine quality policies,objectives and responsibilities(定语从句)",含义为"项目质量管理过程包括决定质量政策、质量目标以及质量责任的什么的所有活动",根据项目质量管理知识,只有组织才可以决定项目的质量政策,因而此处选择选项C。
第2题:
Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to(75) progress.
A.analyze
B.track
C.level
D.extend
第3题:
Scope Management:
A.entails managing the project's work content.
B.is a subset of configuration management and as such is performed by CM specialists.
C.is concerned with naming all activities performed, the end products which results and the resources consumed.
D.is not a concern of the project manager.
E.None of the above.
第4题:
Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups.()process does not belong to Project Integration Management.
A.Developing project charter
B.Developing project management plan
C.Analyzing project risks
D.Monitoring and controlling project
第5题:
The( )provides the project manager with the authority to apply organizational resources to project activities。 A.project management plan B.project charter C.project human resource plan D.project stakeholders
第6题:
● Scope Management:
A entails managing the project's work content.
B is a subset of configuration management and as such is performed by CM specialists.
C is concerned with naming all activities performed, the end products which results and the resources consumed.
D is not a concern of the project manager.
E None of the above.
第7题:
The(70)provides the project manager with the authority to apply organizational resources to project activities.
A.project management plan
B.contract
C.project human resource plan
D.project charter
第8题:
● Project Quality Management processes include all the activities of the (71) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.
(71)
A. project
B. project management team
C. performing organization
D. customer
第9题:
The( )provides the project manager with the authority to apply organizational resources to project activities。
A.project management plan
B.project charter
C.project human resource plan
D.project stakeholders
第10题:
Project Quality Management processes include all the activities of the (75) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.
A.performing organization
B.project management team
C.project
D.customer