4.It __________ eight years to build the Dam(大坝) from 1998 t0 2006.A.spends B.costs C

题目

4.It __________ eight years to build the Dam(大坝) from 1998 t0 2006.

A.spends

B.costs

C.paid

D.took

参考答案和解析
正确答案:D
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

(c) Using information from the case, assess THREE risks to the Giant Dam Project. (9 marks)


正确答案:
(c) Assessment of three risks
Disruption and resistance by Stop-the-dam. Stop-the-dam seems very determined to delay and disrupt progress as much as
possible. The impact of its activity can be seen on two levels. It is likely that the tunnelling and other ‘human’ disruption will
cause a short-term delay but the more significant impact is that of exposing the lenders. In terms of probability, the case says
that it ‘would definitely be attempting to resist the Giant Dam Project when it started’ but the probability of exposing the
lenders is a much lower probability event if the syndicate membership is not disclosed.
Impact/hazard: low
Probability/likelihood: high
The risk to progress offered by First Nation can probably be considered to be low impact/hazard but high probability. The case
says that it ‘would be unlikely to disrupt the building of the dam’, meaning low impact/hazard, but that ‘it was highly likely
that they would protest’, meaning a high level of probability that the risk event would occur.
Impact: low
Probability: high
There are financing risks as banks seems to be hesitant when it comes to lending to R&M for the project. Such a risk event,
if realised, would have a high potential for disruption to progress as it may leave R&M with working capital financing
difficulties. The impact would be high because the bank may refuse to grant or extend loans if exposed (subject to existing
contractual terms). It is difficult to estimate the probability. Perhaps there will be a range of attitudes by the lending banks
with some more reticent than others (perhaps making it a ‘medium’ probability event).
Impact: medium to high (depending on the reaction of the bank)
Probability: low to medium (depending on how easy it would be to discover the lender)

第2题:

根据“职工”项目文件生成emp_sys.exe应用程序的命令是

A.BUILD EXE emp_sys FROM 职工

B.BUILD APP emp_sys.exe FROM 职工

C.LINK EXE emp_sys FROM职工

D.LINK APP emp_sys.exe FROM职工


正确答案:A
解析:连编应用程序命令可以是BUILD APP<新的应用程序名> FROM <项目名,或BUILD EXE<新的可执行程序 名> FROM <项目名>。本题要求生成的文件类型为可执行文件(.exe),应使用 BUILD EXE 命令。

第3题:

He( )English for eight years.

A. has learned

B. learned

C. learns

D. is learning


参考答案:A

第4题:

The International Oil Pollution Prevention Certificate is valid for a period of______.

A.one year from the date of issue

B.five years from the date of issue

C.three years from the date of issue

D.four years from the date of issue


正确答案:B

第5题:

Which factor determines the ring dam size for a fuel oil, tubular bowl type, centrifugal purifier?

A.The viscosity of the fuel.

B.The quantity of water to be removed from the fuel.

C.The specific gravity of the fuel.

D.The quantity of dirt to be removed from the fuel.


正确答案:C

第6题:

He was sixty-eight. In two years he _____ seventy.

A. would be

B. was

C. had been

D. was being


参考答案: A

第7题:

根据“职工”项目文件生成emp_sys.exe应用程序的命令是A)BUILD EXE emp_sys FROM职工B)BUILD APP emp_sys.exe FROM职工C)LINK EXE emp_sys FROM职工D)LINK APP emp_sys.exe FROM职工


正确答案:A
本题考查在Visual FoxPro中应用程序的编译方法。在Visual FoxPro中,可以使用BUILD EXE命令来连编应用程序,其命令格式为:
BUILD EXE 或 BUILD APP
用户还可以通过FROM<项目名>来指定用于生成应用程序的项目文件。故选项A为正确答案,而选项B会生成名为emp_sys.exe.exe的可执行文件,与题干不符。

第8题:

1 Rowlands & Medeleev (R&M), a major listed European civil engineering company, was successful in its bid to become

principal (lead) contractor to build the Giant Dam Project in an East Asian country. The board of R&M prided itself in

observing the highest standards of corporate governance. R&M’s client, the government of the East Asian country, had

taken into account several factors in appointing the principal contractor including each bidder’s track record in large

civil engineering projects, the value of the bid and a statement, required from each bidder, on how it would deal with

the ‘sensitive issues’ and publicity that might arise as a result of the project.

The Giant Dam Project was seen as vital to the East Asian country’s economic development as it would provide a

large amount of hydroelectric power. This was seen as a ‘clean energy’ driver of future economic growth. The

government was keen to point out that because hydroelectric power did not involve the burning of fossil fuels, the

power would be environmentally clean and would contribute to the East Asian country’s ability to meet its

internationally agreed carbon emission targets. This, in turn, would contribute to the reduction of greenhouse gases

in the environment. Critics, such as the environmental pressure group ‘Stop-the-dam’, however, argued that the

project was far too large and the cost to the local environment would be unacceptable. Stop-the-dam was highly

organised and, according to press reports in Europe, was capable of disrupting progress on the dam by measures such

as creating ‘human barriers’ to the site and hiding people in tunnels who would have to be physically removed before

proceeding. A spokesman for Stop-the-dam said it would definitely be attempting to resist the Giant Dam Project when

construction started.

The project was intended to dam one of the region’s largest rivers, thus creating a massive lake behind it. The lake

would, the critics claimed, not only displace an estimated 100,000 people from their homes, but would also flood

productive farmland and destroy several rare plant and animal habitats. A number of important archaeological sites

would also be lost. The largest community to be relocated was the indigenous First Nation people who had lived on

and farmed the land for an estimated thousand years. A spokesman for the First Nation community said that the ‘true

price’ of hydroelectric power was ‘misery and cruelty’. A press report said that whilst the First Nation would be unlikely

to disrupt the building of the dam, it was highly likely that they would protest and also attempt to mobilise opinion in

other parts of the world against the Giant Dam Project.

The board of R&M was fully aware of the controversy when it submitted its tender to build the dam. The finance

director, Sally Grignard, had insisted on putting an amount into the tender for the management of ‘local risks’. Sally

was also responsible for the financing of the project for R&M. Although the client was expected to release money in

several ‘interim payments’ as the various parts of the project were completed to strict time deadlines, she anticipated

a number of working capital challenges for R&M, especially near the beginning where a number of early stage costs

would need to be incurred. There would, she explained, also be financing issues in managing the cash flows to R&M’s

many subcontractors. Although the major banks financed the client through a lending syndicate, R&M’s usual bank

said it was wary of lending directly to R&M for the Giant Dam Project because of the potential negative publicity that

might result. Another bank said it would provide R&M with its early stage working capital needs on the understanding

that its involvement in financing R&M to undertake the Giant Dam Project was not disclosed. A press statement from

Stop-the-dam said that it would do all it could to discover R&M’s financial lenders and publicly expose them. Sally

told the R&M board that some debt financing would be essential until the first interim payments from the client

became available.

When it was announced that R&M had won the contract to build the Giant Dam Project, some of its institutional

shareholders contacted Richard Markovnikoff, the chairman. They wanted reassurance that the company had fully

taken the environmental issues and other risks into account. One fund manager asked if Mr Markovnikoff could

explain the sustainability implications of the project to assess whether R&M shares were still suitable for his

environmentally sensitive clients. Mr Markovnikoff said, through the company’s investor relations department, that he

intended to give a statement at the next annual general meeting (AGM) that he hoped would address these

environmental concerns. He would also, he said, make a statement on the importance of confidentiality in the

financing of the early stage working capital needs.

(a) Any large project such as the Giant Dam Project has a number of stakeholders.

Required:

(i) Define the terms ‘stakeholder’ and ‘stakeholder claim’, and identify from the case FOUR of R&M’s

external stakeholders as it carries out the Giant Dam Project; (6 marks)


正确答案:
(a) (i) Stakeholders
A stakeholder can be defined as any person or group that can affect or be affected by an entity. In this case, stakeholders
are those that can affect or be affected by the building of the Giant Dam Project. Stakeholding is thus bi-directional.
Stakeholders can be those (voluntarily or involuntarily) affected by the activities of an organisation or the stakeholder
may be seeking to influence the organisation in some way.
All stakeholding is characterised by the making of ‘claims’ upon an organisation. Put simply, stakeholders ‘want
something’ although in some cases, the ‘want’ may not be known by the stakeholder (such as future generations). It is
the task of management to decide on the strengths of each stakeholder’s claim in formulating strategy and in making
decisions. In most situations it is likely that some stakeholder claims will be privileged over others.
R&M’s external stakeholders include:
– The client (the government of the East Asian country)
– Stop-the-dam pressure group
– First Nation (the indigenous people group)
– The banks that will be financing R&M’s initial working capital
– Shareholders

第9题:

The International Oil Pollution Prevention Certificate is valid for a period of

A.one year from the date of issue

B.five years from the date of issue

C.three years from the date of issue

D.four years from the date of issue


正确答案:B

第10题:

The transmission media used t0 build a LAN is(73).

A.twisted pair

B.microwave

C.optieal fiber

D.satellitic signal


正确答案:A
解析:四个选项分别是双绞线、微波、光纤和卫星信号,其中双绞线价格低廉、通信距离短,适合用于LAN。

更多相关问题