6 Typically, during which phase in a project life cycle are most of the project expenses incurred. A. Concept phase
B Development of design phase
C. Execution phase.
D. Termination phase.
E. None of the above
第1题:
The project stakeholders should be actively involved with the _____ phase(s) of the life cycle.
A.Conceptual
B.Development.
C.Execution
D.Finish
E.All of the above.
第2题:
Typically, during which phase in a project life cycle are most of the project expenses incurred.
A . Concept phase
B . Development of design phase
C . Execution phase.
D . Termination phase.
E . None of the above
第3题:
Which of the following are included in the Acquisition phase(s) of the project life cycle.
A . concept and development
B . development and planning
C . execution and phase-out
D . planning and implementation
E . concept and planning
第4题:
70 Which phase of the project life cycle typically has the highest uncertainty and risk associated with it? A. concept
B. development
C. execution
D. conclusion
E. All of the above
第5题:
Which phase of the project life cycle typically has the highest uncertainty and risk associated with it?
A concept
B development
C execution
D conclusion
E All of the above.
第6题:
QUEST . Which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?
A . 5%
B . 10%
C . 15%
D . 25%
E . 50%
第7题:
During which phase of the project life cycle is the amount at stake lowest?
A concept
B development
C execution
D conclusion
E C and D
第8题:
The project life-cycle can be described as:
A.project concept, project planning, project execution, and project close-out.
B.project planning, work authorization, and project reporting.
C.project planning, project control, project definition, WBS development, and project termination.
D.project concept, project execution, and project reporting.
E.All of the above.
第9题:
67 The project stakeholders should be actively involved with the _____ phase(s) of the life cycle. A. Conceptual
B. Development.
C. Execution
D. Finish
E. All of the above
第10题:
95 Which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?
A. 5%
B. 10%
C. 15%
D. 25%
E. 50%