148 Network schedules are prepared during the _____ phase and updated during the _____ phase. A. Conceptual, execution.
B. Development, implementation.
C. Development, close-out.
D. Implementation, close-out.
E. Planning, finishing
第1题:
Make or buy decisions are usually made during the _____ phase of a project.
A.Conceptual
B.Development.
C.Implementation
D.Execution
E.Close-out
第2题:
Network schedules are prepared during the _____ phase and updated during the _____ phase.
A.Conceptual, execution.
B.Development, implementation.
C.Development, close-out.
D.Implementation, close-out.
E.Planning, finishing.
第3题:
Which of the following are included in the Acquisition phase(s) of the project life cycle.
A . concept and development
B . development and planning
C . execution and phase-out
D . planning and implementation
E . concept and planning
第4题:
6 Typically, during which phase in a project life cycle are most of the project expenses incurred. A. Concept phase
B Development of design phase
C. Execution phase.
D. Termination phase.
E. None of the above
第5题:
130 The identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives are indentified in the _____ phase of the project but first documented in the project _____.
A. Conceptual, charter/baseline.
B. Conceptual, master schedule.
C. Development, charter/baseline.
D. Development, master schedule.
E. Development, masterplan
第6题:
The identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives are indentified in the _____ phase of the project but first documented in the project _____.
A.Conceptual, charter/baseline.
B.Conceptual, master schedule.
C.Development, charter/baseline.
D.Development, master schedule.
E.Development, masterplan.
第7题:
Typically, during which phase in a project life cycle are most of the project expenses incurred.
A . Concept phase
B . Development of design phase
C . Execution phase.
D . Termination phase.
E . None of the above
第8题:
Project life cycles provide a better means of measurement of progress and control. The four phases of a project are conceptual development, _____, _____, and _____.
APreliminary planning, detail planning, closeout
BImplementation, reporting, termination
CDevelopment, implementation, termination
DExecution, reporting, finishing
EImplementation, termination, post-audit review
第9题:
62 Make or buy decisions are usually made during the _____ phase of a project.
A. Conceptual
B. Development.
C. Implementation
D. Execution
E. Close-out
第10题:
92 Project life cycles provide a better means of measurement of progress and control. The four phases of a project are conceptual development, _____, _____, and _____.
A. Preliminary planning, detail planning, closeout
B. Implementation, reporting, termination
C. Development, implementation, termination
D. Execution, reporting, finishing
E. Implementation, termination, post-audit review