Precedence Diagramming Method(PDM) is a method used in activity sequencing. There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends u

题目
Precedence Diagramming Method(PDM) is a method used in activity sequencing. There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called ( ).

A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

On a precedence diagram, the arrow between two boxes is called:

A.An activity.

B.A constraint.

C.An event.

D.The critical path.

E.None of above.


正确答案:B
B

第2题:

PDM includes four types of dependencies or precedence relationships: (). The completion of the successor activity depends upon the initiation of the predecessor activity.

A.Finish-to-Start

B.Finish-to-Finish

C.Start-to-Start

D.Start-to-Finish


参考答案:B

第3题:

The most frequently used construct in Precedent Diagramming Method is:

A.Start to Start.

B.Finish to Finish.

C.Start to Finish.

D.Finish to Start.

E.Dummy activity.


正确答案:D
D

第4题:

______is one of the techniques used for estimating activity durations.

A.Analogous Estimating

B.Precedence Diagramming Method(PDM)

C.Dependency Determination

D.Schedule network Templates


正确答案:A
解析:下列用于活动历时估算的技术是答案A类比估算法。

第5题:

● ADM is an activity-on-arrow method. In this method, a dummy activity:

A Denotes a critical path relationship.

B Denotes any dependency relationship.

C Shows slack.

D Identifies customer deliverables dates.

E Identifies customer team meeting dates.


正确答案:B

第6题:

PDM includes four types of dependencies or precedence relationships:().The completion ofthe successor activity depends upon the initiation of the predecessor activity.

A.Finish-to-Start

B.Finish-to-Finish

C.Start-to-Start

D.Start-to-Finish


参考答案:D

该题的关键词为"PDM includes four types",其语句结构为"The completion of the successor activity(主语)depends upon(谓语)the initiation of the predecessor activity",含义为"后续活动的完成依赖于前置活动的开始",根据选项容易识别为SF活动依赖类型。

第7题:

● The most frequently used construct in Precedent Diagramming Method is:

A Start to Start.

B Finish to Finish.

C Start to Finish.

D Finish to Start.

E Dummy activity.


正确答案:D

第8题:

ADM is an activity-on-arrow method. In this method, a dummy activity:

A.Denotes a critical path relationship.

B.Denotes any dependency relationship.

C.Shows slack.

D.Identifies customer deliverables dates.

E.Identifies customer team meeting dates.


正确答案:B
B

第9题:

● (73) is one of the techniques used for estimating activity durations.

(73)

A.Analogous Estimating

B.Precedence Diagramming Method (PDM)

C.Dependency Determination

D.Schedule network Templates


正确答案:A
试题(73)分析
    下列用于活动历时估算的技术是答案A类比估算法。
参考答案
    (73)A

第10题:

● (73) is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist between

them.

(73)

A.PERT

B.AOA

C.WBS

D.PDM


正确答案:D

试题(73)分析
    (73)  用于关键路径法,是用于编制项目进度网络图的一种方法,它使用方框或者长方形(被称作节点)代表活动,它们之间用箭头连接,显示彼此之间存在的逻辑关系。
  A.PERT            B.AOA             C.WBS             D.PDM
参考答案
  (73)D