第1题:
On a precedence diagram, the arrow between two boxes is called:
A.An activity.
B.A constraint.
C.An event.
D.The critical path.
E.None of above.
第2题:
A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish
第3题:
The most frequently used construct in Precedent Diagramming Method is:
A.Start to Start.
B.Finish to Finish.
C.Start to Finish.
D.Finish to Start.
E.Dummy activity.
第4题:
______is one of the techniques used for estimating activity durations.
A.Analogous Estimating
B.Precedence Diagramming Method(PDM)
C.Dependency Determination
D.Schedule network Templates
第5题:
● ADM is an activity-on-arrow method. In this method, a dummy activity:
A Denotes a critical path relationship.
B Denotes any dependency relationship.
C Shows slack.
D Identifies customer deliverables dates.
E Identifies customer team meeting dates.
第6题:
A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish
该题的关键词为"PDM includes four types",其语句结构为"The completion of the successor activity(主语)depends upon(谓语)the initiation of the predecessor activity",含义为"后续活动的完成依赖于前置活动的开始",根据选项容易识别为SF活动依赖类型。
第7题:
● The most frequently used construct in Precedent Diagramming Method is:
A Start to Start.
B Finish to Finish.
C Start to Finish.
D Finish to Start.
E Dummy activity.
第8题:
ADM is an activity-on-arrow method. In this method, a dummy activity:
A.Denotes a critical path relationship.
B.Denotes any dependency relationship.
C.Shows slack.
D.Identifies customer deliverables dates.
E.Identifies customer team meeting dates.
第9题:
● (73) is one of the techniques used for estimating activity durations.
(73)
A.Analogous Estimating
B.Precedence Diagramming Method (PDM)
C.Dependency Determination
D.Schedule network Templates
第10题:
● (73) is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist between
them.
(73)
A.PERT
B.AOA
C.WBS
D.PDM