第1题:
A Work Breakdown Structure:
A.assures all work is identified
B.subdivides the project into manageable segments
C.provides the project sponsor with a time-phase task summary
D.both A and B
E.All of the above.
第2题:
The primary source document for establishing the content of the Project Status Report is:
A The project charter
B The Project Plan
C The ASTM Project Document Guide
D The summary work breakdown structure
第3题:
The work breakdown structure (WBS) is first developed in which scope management process?
A . Initiation
B . Scope planning
C . Scope change control
D . Scope Definition
E . Scope verification
第4题:
23 The work breakdown structure (WBS) is first developed in which scope management process? A. Initiation
B. Scope planning
C. Scope change control
D. Scope
Definition
E. Scope verification
第5题:
94 The primary source document for establishing the content of the Project Status Report is:
A. The project charter
B. The Project Plan
C. The ASTM Project Document Guide
D. The summary work breakdown structure
第6题:
The Work Breakdown Structure (WBS) is the basis for communicating:
A.Project scope, cost control, schedule, quality
B.Project objectives, dependencies, plan, cost control
C.Project scope, schedule, staffing, cost control
D.Project scope, quality, schedule, dependencies
E.Project budget, schedule, risk factors, work assignments.
第7题:
63 When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the
A. task
B. level of effort
C. sub-task
D. project
E. work package
第8题:
When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the
A.task
B.level of effort
C.sub-task
D.project
E.work package
第9题:
141 The work breakdown structure (WBS) is first developed in which scope management process? A. Initiation
B. Scope planning
C. Scope change control
D. Scope Definition
E. Scope verification
第10题:
● When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the
A task
B level of effort
C sub-task
D project
E work package