The work breakdown structure (WBS) has been widely used in management for software development project, ( ) is generally NOT validated through the WBS.
A.Schedule and cost
B.Organization structuring
C.Management coordination
D.Quality of work
第1题:
The Work Breakdown Structure (WBS) is the basis for communicating:
A.Project scope, cost control, schedule, quality
B.Project objectives, dependencies, plan, cost control
C.Project scope, schedule, staffing, cost control
D.Project scope, quality, schedule, dependencies
E.Project budget, schedule, risk factors, work assignments.
第2题:
The "control points" in the work breakdown structure used for isolated assignments to work centers are referred to as:
A.Work packages.
B.Subtasks.
C.Tasks.
D.Code of accounts.
E.Integration points.
第3题:
The work breakdown structure (WBS) is first developed in which scope management process?
A . Initiation
B . Scope planning
C . Scope change control
D . Scope Definition
E . Scope verification
第4题:
141 The work breakdown structure (WBS) is first developed in which scope management process? A. Initiation
B. Scope planning
C. Scope change control
D. Scope Definition
E. Scope verification
第5题:
106 The "control points" in the work breakdown structure used for isolated assignments to work centers are referred to as:
A. Work packages.
B. Subtasks.
C. Tasks.
D. Code of accounts.
E. Integration points
第6题:
The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?
A.Time, schedule and cost.
B.Management coordination and organization structuring.
C.Work methods and accountability.
D.Quality of work.
E.Risk and impact decision-making.
第7题:
The most effective means of determining the cost of a project is to price out the _____.
A . Work breakdown structure.
B . Linear responsibility chart.
C . Project charter.
D . Scope statement.
E . Management plan.
第8题:
When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the
A.task
B.level of effort
C.sub-task
D.project
E.work package
第9题:
198 The most effective means of determining the cost of a project is to price out the _____.
A. Work breakdown structure.
B. Linear responsibility chart.
C. Project charter.
D. Scope statement.
E. Management plan
第10题:
23 The work breakdown structure (WBS) is first developed in which scope management process? A. Initiation
B. Scope planning
C. Scope change control
D. Scope
Definition
E. Scope verification