第1题:
The project life-cycle can be described as:
A.project concept, project planning, project execution, and project close-out.
B.project planning, work authorization, and project reporting.
C.project planning, project control, project definition, WBS development, and project termination.
D.project concept, project execution, and project reporting.
E.All of the above.
第2题:
A project manager can exchange information with the project team using which media?
A tactile
B audio
C olfactory
D visual
E All of the above.
第3题:
A program can best be described as:
AA grouping of related activities which last two years or more
BThe first major subdivision of a project
CA grouping of projects, similar in nature, which support a product or product line and have no definable end point
DA product line
EAnother name for a project
第4题:
193 Creation of project objectives:
A. allows for data collection and analysis and progress reporting against which standards of performance can be measured.
B. is accomplished by selection of measurable variables against which performance can be judged. C. is required before funding of the project by the project sponsor.
D. all of the above.
E. A and B only
第5题:
Total project risk can be defined as:
A the sum of the probabilities of project risks events times the sum of consequences of those risks
B the sum of the products of each project risk event times its consequences
C the sum of the consequences of all project risk events
D the sum of the probabilities of all project risk events
E 1 - the sum of the probabilities of all project risk events.
第6题:
Team members want to work for a project manager that can provide them with career path planning. In which organizational form. is career path planning difficult for project employees?
A . Matrix
B . Pure project
C . Project coordinator
D . Project expediter
E . Classical/traditional
第7题:
Project Risk Management is based on which of the following premises:
A the future is unknown.
B unknowns can result in risks or opportunities.
C we cannot control risk events.
D project risk impact can be measured and controlled
E All of the above.
第8题:
Creation of project objectives:
A.allows for data collection and analysis and progress reporting against which standards of performance can be measured.
B.is accomplished by selection of measurable variables against which performance can be judged.
C.is required before funding of the project by the project sponsor.
D.all of the above.
E.A and B only
第9题:
167 The project life-cycle can be described as:
A. project concept, project planning, project execution, and project close-out.
B. project planning, work authorization, and project reporting.
C. project planning, project control, project definition, WBS development, and project termination. D. project concept, project execution, and project reporting.
E. All of the above
第10题:
109 Problems can occur in properly defining a project because:
A. Project goals may not be agreeable to all parties
B. The plan was "too loose," thus allowing priorities to change
C. Low turnover of project personnel
D. Too much communication between the client and project personnel
E. The project objectives were quantified