第1题:
108 Risk mitigation is the process of _____ .
A. transferring risk to another party.
B. reducing uncertainty on the project
C. identifying all possible risk events
D. monitoring status and making adjustments
E. All of the above
第2题:
The( )process ascertains which risks have the potential of affecting the project and documenting the risks’characteristics. A.Risk Identification B.Quantitative Risk Analysis C.Qualitative Risk Analysis D.Risk Monitoring and Control
第3题:
Risk mitigation is the process of _____ .
A transferring risk to another party.
B reducing uncertainty on the project
C identifying all possible risk events
D monitoring status and making adjustments
E All of the above.
第4题:
setting redundant components in subsystem to handle with the risks brought by the defaultsof original components,what kind of risk response strategy is this?()
A.risk avoidance
B.risk acceptance
C.risk mitigation
D.contingency plan
第5题:
●Managing risk and documenting them is very important in project planning process. You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the (73).
(73)A. project management plan
B. project baseline
C. risk response plan
D. risk baseline
第6题:
Risk management allows the project manager and the project team not to(71). A.eliminate most risks during the planning phase of the project B.identify project risks C.identify impacts of various risks D.plan suitable responses
第7题:
The()process analyzes the effect of risk events and assigns a numerical rating to those risks.()A.Risk Identification B.Quantitative Risk AnalysisC.Qualitative Risk Analysis D.Risk Monitoring and Control
第8题:
26 Risk mitigation is the process of _____ .
A. transferring risk to another party.
B. reducing uncertainty on the project
C. identifying all possible risk events
D. monitoring status and making adjustments
E. All of the above.
第9题:
Setting redundant components in subsystem to handle with the risks brought by the defaults of original components, what kind of risk response strategy is this ? ( 75 ).
A.Risk avoidance
B.Risk acceptance
C.Risk mitigation
D.Contingency plan
第10题:
()is the process of implementing risk response plans,tracking identified risks,monitoring residual risk,identifying new risk,and evaluating risk process effectiveness throughout the project.
A.Identity risks
B.Control risks
C.Plan risk responses
D.Plan risk management