( )is the process of implementing risk response plants,tracking?identified risks,monitoring residual risk,identifying new risk,and ecaluating risk process effectiveness throughout the project.A.Identity risks B.Control risks C.Plan risk responses D.Plan r

题目
( )is the process of implementing risk response plants,tracking?identified risks,monitoring residual risk,identifying new risk,and ecaluating risk process effectiveness throughout the project.

A.Identity risks
B.Control risks
C.Plan risk responses
D.Plan risk management
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

108 Risk mitigation is the process of _____ .

A. transferring risk to another party.

B. reducing uncertainty on the project

C. identifying all possible risk events

D. monitoring status and making adjustments

E. All of the above


正确答案:B

第2题:

The( )process ascertains which risks have the potential of affecting the project and documenting the risks’characteristics. A.Risk Identification B.Quantitative Risk Analysis C.Qualitative Risk Analysis D.Risk Monitoring and Control


正确答案:A
风险识别(RiskIdentification)是确定何种风险可能会对项目产生影响,并将这些风险的特征形成文档。

第3题:

Risk mitigation is the process of _____ .

A transferring risk to another party.

B reducing uncertainty on the project

C identifying all possible risk events

D monitoring status and making adjustments

E All of the above.


正确答案:B

第4题:

setting redundant components in subsystem to handle with the risks brought by the defaultsof original components,what kind of risk response strategy is this?()

A.risk avoidance

B.risk acceptance

C.risk mitigation

D.contingency plan


正确答案:C
设置冗余组件的子系统处理的原始成分的违约带来的风险,这是一种什么样的风险应对策略?()A、风险规避B、风险接受C、风险减轻D、应急计划

第5题:

●Managing risk and documenting them is very important in project planning process. You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the (73).

(73)A. project management plan

B. project baseline

C. risk response plan

D. risk baseline


正确答案:A

第6题:

Risk management allows the project manager and the project team not to(71). A.eliminate most risks during the planning phase of the project B.identify project risks C.identify impacts of various risks D.plan suitable responses


正确答案:A
风险管理并不能使得项目经理及其团队在项目的规划过程中避免大多数的风险。

第7题:

The()process analyzes the effect of risk events and assigns a numerical rating to those risks.()A.Risk Identification B.Quantitative Risk AnalysisC.Qualitative Risk Analysis D.Risk Monitoring and Control


正确答案:B
定量风险分析过程分析风险事件的影响并对这些影响赋予一个数值化的评价。

第8题:

26 Risk mitigation is the process of _____ .

A. transferring risk to another party.

B. reducing uncertainty on the project

C. identifying all possible risk events

D. monitoring status and making adjustments

E. All of the above.


正确答案:B

第9题:

Setting redundant components in subsystem to handle with the risks brought by the defaults of original components, what kind of risk response strategy is this ? ( 75 ).

A.Risk avoidance

B.Risk acceptance

C.Risk mitigation

D.Contingency plan


正确答案:C

第10题:

()is the process of implementing risk response plans,tracking identified risks,monitoring residual risk,identifying new risk,and evaluating risk process effectiveness throughout the project.

A.Identity risks

B.Control risks

C.Plan risk responses

D.Plan risk management


正确答案:B