SWOT analysis is a kind of risk identification method. If the project team chose the SO strategy, they should()

题目
SWOT analysis is a kind of risk identification method. If the project team chose the SO strategy, they should()

A.make full use of the advantage and catch the opportunity
B.overcome the weakness and catch the opportunity
C.make full use of the advantage and reduce the threat
D.overcome the weakness and reduce the threat
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

Sensitivity analysis can be used in risk analysis to:

A Substitute for uncertainty analysis in risk quantification

B estimate the level of risk aversion adopted by management

C estimate the effect of change of one project variable on the overall project

D A and B

E All of the above.


正确答案:C

第2题:

Risk management allows the project manager and the project team to:

A eliminate most risks during the planning phase of the project

B identify project risks

C identify impacts of various risks

D plan suitable responses

E B, C and D only


正确答案:E

第3题:

A project manager trying to communicate accurately to the team should use:

A the language of the team members

B the language of the project manager

C non-verbal methods

D written memos

E All of the above.


正确答案:A

第4题:

157 Sensitivity analysis can be used in risk analysis to:

A. Substitute for uncertainty analysis in risk quantification

B. estimate the level of risk aversion adopted by management

C. estimate the effect of change of one project variable on the overall project

D. A and B

E. All of the above


正确答案:C

第5题:

193 A project manager trying to communicate accurately to the team should use:

A. the language of the team members

B. the language of the project manager

C. non-verbal methods

D. written memos

E. All of the above.


正确答案:A

第6题:

Total Project Risk:

A should not be calculated for small projects

B is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.

C Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.

D A and B

E A and C


正确答案:C

第7题:

84 Risk management allows the project manager and the project team to:

A. eliminate most risks during the planning phase of the project

B. identify project risks

C. identify impacts of various risks

D. plan suitable responses

E. B, C and D only


正确答案:E

第8题:

Risk mitigation includes all but which of the following:

A Developing system (policies, procedures, responsibilities)

B Obtaining insurance against loss

C performing contingent planning

D developing planning alternatives

E identification of project risks.


正确答案:E

第9题:

122 Total Project Risk:

A. should not be calculated for small projects

B. is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.

C. Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.

D. A and B

E. A and C


正确答案:C

第10题:

75 A project manager trying to communicate accurately to the team should use:

A. the language of the team members

B. the language of the project manager

C. non-verbal methods

D. written memos

E. All of the above


正确答案:A

更多相关问题