第1题:
A Work Breakdown Structure:
A.assures all work is identified
B.subdivides the project into manageable segments
C.provides the project sponsor with a time-phase task summary
D.both A and B
E.All of the above.
第2题:
The starting point in the development of a top-down PERT/CPM chart is the _____ .
A.Project specification tree.
B.Customer's deliverable list.
C.Customer's milestone dates.
D.Work breakdown structure.
E.Listing of customer team meeting dates.
第3题:
A work breakdown structure:
A . assures all work is identified.
B . subdivides the project into manageable segments.
C . provides the project sponsor with a time-phase task summary.
D . both A and B.
E . All of the above.
第4题:
111 It is useful to conduct project risk assessment according to the project's
A. charter
B. statement of work
C. Work Breakdown structure
D. network
E. budget
第5题:
Giving a part of project work to a contractor is an example of:
A risk mitigation
B risk assignment
C risk delegation
D risk deflection
E risk assumption
第6题:
The Work Breakdown Structure (WBS) is the basis for communicating:
A.Project scope, cost control, schedule, quality
B.Project objectives, dependencies, plan, cost control
C.Project scope, schedule, staffing, cost control
D.Project scope, quality, schedule, dependencies
E.Project budget, schedule, risk factors, work assignments.
第7题:
The primary source document for establishing the content of the Project Status Report is:
A The project charter
B The Project Plan
C The ASTM Project Document Guide
D The summary work breakdown structure
第8题:
When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the
A.task
B.level of effort
C.sub-task
D.project
E.work package
第9题:
It is useful to conduct project risk assessment according to the project's
A charter
B statement of work
C Work Breakdown structure
D network
E budget
第10题:
63 When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the
A. task
B. level of effort
C. sub-task
D. project
E. work package