单选题Team member listing, scheduled tasks, and risk identification are part of the:()A project plan.B project charter.C communication plan.D WBS (Work Breakdown Structure).

题目
单选题
Team member listing, scheduled tasks, and risk identification are part of the:()
A

project plan.

B

project charter.

C

communication plan.

D

WBS (Work Breakdown Structure).

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

A Work Breakdown Structure:

A.assures all work is identified

B.subdivides the project into manageable segments

C.provides the project sponsor with a time-phase task summary

D.both A and B

E.All of the above.


正确答案:D
D

第2题:

The starting point in the development of a top-down PERT/CPM chart is the _____ .

A.Project specification tree.

B.Customer's deliverable list.

C.Customer's milestone dates.

D.Work breakdown structure.

E.Listing of customer team meeting dates.


正确答案:D
D

第3题:

A work breakdown structure:

A . assures all work is identified.

B . subdivides the project into manageable segments.

C . provides the project sponsor with a time-phase task summary.

D . both A and B.

E . All of the above.


正确答案:D

 

第4题:

111 It is useful to conduct project risk assessment according to the project's

A. charter

B. statement of work

C. Work Breakdown structure

D. network

E. budget


正确答案:C

第5题:

Giving a part of project work to a contractor is an example of:

A risk mitigation

B risk assignment

C risk delegation

D risk deflection

E risk assumption


正确答案:D

第6题:

The Work Breakdown Structure (WBS) is the basis for communicating:

A.Project scope, cost control, schedule, quality

B.Project objectives, dependencies, plan, cost control

C.Project scope, schedule, staffing, cost control

D.Project scope, quality, schedule, dependencies

E.Project budget, schedule, risk factors, work assignments.


正确答案:A
A

第7题:

The primary source document for establishing the content of the Project Status Report is:

A The project charter

B The Project Plan

C The ASTM Project Document Guide

D The summary work breakdown structure


正确答案:B

第8题:

When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the

A.task

B.level of effort

C.sub-task

D.project

E.work package


正确答案:E

第9题:

It is useful to conduct project risk assessment according to the project's

A charter

B statement of work

C Work Breakdown structure

D network

E budget


正确答案:C

第10题:

63 When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the

A. task

B. level of effort

C. sub-task

D. project

E. work package


正确答案:E

更多相关问题