第1题:
(b) As a newly-qualified Chartered Certified Accountant in Boleyn & Co, you have been assigned to assist the ethics
partner in developing ethical guidance for the firm. In particular, you have been asked to draft guidance on the
following frequently asked questions (‘FAQs’) that will be circulated to all staff through Boleyn & Co’s intranet:
(i) What Information Technology services can we offer to audit clients? (5 marks)
Required:
For EACH of the three FAQs, explain the threats to objectivity that may arise and the safeguards that should
be available to manage them to an acceptable level.
NOTE: The mark allocation is shown against each of the three questions.
第2题:
A. Guessing game
B. Information-gap.
C. Story telling
D. Drama performance.
第3题:
The Cost Performance Index is computed as:
A . budget cost of work performed divided by actual cost of work performed
B . budget cost of work performed minus actual cost of work performed
C . budget cost of work performed minus budget cost of work scheduled
D . budget cost of work scheduled divided by budget cost of work performed
E . actual cost of work scheduled divided by budget cost of work performed
第4题:
Cooling water is circulated through______in some injectors.
A.the nozzle
B.the nozzle tip
C.the internal passages
D.the fuel re-circulated
第5题:
● The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that __(74)__.
(74)A.the project is ahead of its planned schedule
B.less work was completed than was planned
C.the cost overrun for work completed
D.the cost under-run of performance to date
第6题:
The earned value technique is a commonly used method of performance measurement.It integrates project scope,schedule,and cost measures to help the project management team assess project performance.If a project’s Cost Performance Index(CPI=EV/AC)value less than 1.0,it means that( )。 A.the cost savings for work completed B.the project is ahead of its planned schedule C.the cost overrun for work completed D.1ess work was completed than was planned
第7题:
A.none of them
B.information sharing
C.information opening
D.information flowing
E.Information management
第8题:
114 The Cost Performance Index is computed as:
A. budget cost of work performed divided by actual cost of work performed
B. budget cost of work performed minus actual cost of work performed
C. budget cost of work performed minus budget cost of work scheduled
D. budget cost of work scheduled divided by budget cost of work performed
E. actual cost of work scheduled divided by budget cost of work performed
第9题:
The earned value technique is a commonlyused method of performance measurement. It integrates project scope, cost, andschedule measures to help the project management team assess projectperformance.If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, itmeans that (74).
A.the project is ahead of its planned schedule
B.less work was completed than was planned
C.the cost overrun for work completed
D.the cost under-run of performance to date
第10题:
In terms of vessel manning,a watch is the ______.
A.direct performance of deck or engine operations in a scheduled and fixed rotation
B.performance of maintenance work necessary for the vessel's safe operation,on a daily basis
C.performance of lookout duties
D.direct performance of cargo loading and discharge operations only