Your project is behind schedule

题目

Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().

  • A、crashing the schedule
  • B、performing resource leveling
  • C、conducting reverse resource allocation scheduling
  • D、utilizing the critical chain resources
参考答案和解析
正确答案:A
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

The identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives are indentified in the _____ phase of the project but first documented in the project _____.

A.Conceptual, charter/baseline.

B.Conceptual, master schedule.

C.Development, charter/baseline.

D.Development, master schedule.

E.Development, masterplan.


正确答案:A
A

第2题:

A negative cost variance and positive schedule variance means:

A The project is under budget and ahead of schedule

B The project is over budget and behind schedule

C The project is over budget and ahead of schedule

D The project will be overrun but ahead of schedule at completion


正确答案:C

第3题:

The most common non-behavioral reason for projects being completed behind schedule and over budget is:

ASelecting the wrong person as the project manager

BSelecting the wrong person as the sponsor

CAccepting a high-risk project

DIll-defined requirements

EAll of the above


正确答案:D

第4题:

● The Work Breakdown Structure (WBS) is the basis for communicating:

A Project scope, cost control, schedule, quality

B Project objectives, dependencies, plan, cost control

C Project scope, schedule, staffing, cost control

D Project scope, quality, schedule, dependencies

E Project budget, schedule, risk factors, work assignments.


正确答案:A

第5题:

96 A negative cost variance and positive schedule variance means:

A. The project is under budget and ahead of schedule

B. The project is over budget and behind schedule

C. The project is over budget and ahead of schedule

D. The project will be overrun but ahead of schedule at completion


正确答案:C

第6题:

During a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12% of the work scheduled to this point of time. You can therefore conclude that:

A . The project will be completed late.

B . The critical path has been lengthened.

C . the costs are being overrun.

D . Overtime will be required to maintain the original critical path.

E . None of the above.


正确答案:E

第7题:

38 The most common non-behavioral reason for projects being completed behind schedule and over budget is:

A. Selecting the wrong person as the project manager

B. Selecting the wrong person as the sponsor

C. Accepting a high-risk project

D. Ill-defined requirements

E. All of the above


正确答案:D

第8题:

The Work Breakdown Structure (WBS) is the basis for communicating:

A.Project scope, cost control, schedule, quality

B.Project objectives, dependencies, plan, cost control

C.Project scope, schedule, staffing, cost control

D.Project scope, quality, schedule, dependencies

E.Project budget, schedule, risk factors, work assignments.


正确答案:A
A

第9题:

● The most common non-behavioral reason for projects being completed behind schedule and over budget is:

A Selecting the wrong person as the project manager

B Selecting the wrong person as the sponsor

C Accepting a high-risk project

D Ill-defined requirements

E All of the above


正确答案:D

第10题:

Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to(75) progress.

A.analyze

B.track

C.level

D.extend


正确答案:B
解析:通常,制订项目进度计划是一个反复迭代的过程,该过程确定每个活动和每个里程碑的开工日期和完成日期。制订进度过程要求对历时估算和资源估算进行评审和修订,从而产生一个经过认可的项目进度表,作为对项目进展进行追踪的基准。

更多相关问题