单选题A technical specialist has a requirement to implement a 4-way POWER5 server with a small Web server partition and a high performance database server partition. The Web server provides a client front-end to the database server. The most important concer

题目
单选题
A technical specialist has a requirement to implement a 4-way POWER5 server with a small Web server partition and a high performance database server partition. The Web server provides a client front-end to the database server. The most important concerns are speed of communication between the Web server and the database and I/O speed of the database. Which of the following virtualization features would be most appropriate?()
A

Virtual SCSI

B

Virtual Ethernet

C

Virtual I/O Server

D

Micro-Partitioning

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

Which components are installed on the middle tier in a WebSphere Commerce V 5.6 three-tier configuration (i.e. in a three-node topology)?()

  • A、WebSphere Commerce Server, WebSphere Application Server and Web server plugin
  • B、WebSphere Application Server, Database Client and Web server plugin
  • C、WebSphere Commerce Server, Database Server and WebSphere Application Server
  • D、WebSphere Commerce Server, WebSphere Application Server and Database Client
  • E、Web server, WebSphere Commerce Server and WebSphere Application Server

正确答案:D

第2题:

A technical specialist has installed a Host Bus Adapter (HBA) on a p5-550 server. The system has four AIX 5L V5.3 partitions and a Virtual I/O server. The HBA will be used to connect all four partitions to a DS8000 storage array. What else must be performed to make the storage available to the partitions?()

  • A、Allocate the HBA to a client partition.
  • B、Restart the Virtual I/O Server to detect the changes.
  • C、Install the device driver for the DS8000 in each of the four AIX partitions.
  • D、Allocate the HBA to the VIO server partition and install necessary drivers.

正确答案:D

第3题:

You are the administrator of two SQL Server 2000 computers. One of these servers contains a 4-GB database named marketing. You want to remove the marketing database from one server and add it to the other as quickly as possible.

What should you do?

A.Detach the database from the original server by using the sp_detach_db stored procedure. Copy the database and the transaction log files to the new server, and attach them by using the sp_attach_db stored procedure.

B.Use the DTS export wizard to transfer all database objects from the original server to the new server. Drop the database from the original server.

C.Run a full backup of the database on the original server. Create a new database named marketing on the new server. Restore the backup in the new marketing database. Drop the database from the original server.

D.Shut down the original server. Copy the database and the transaction log files to the new server. Use the DISK INIT and DISK REFIT statements to attach the data file to the new server. Drop the database from the original server.


正确答案:A
解析:Explanation:Detachingandattachingdatabasesissometimesausefultechniqueforquicklymovingadatabasefromonecomputertoanother.Tomoveadatabase,ordatabasefile,toanotherserverordiskthedatabasemustfirstbedetachedfromtheoriginalserverordisk;movedtotheotherserverordiskandthenattachedontheserverordisk.Inadditionthenewlocationofthemovedfile(s)mustbespecified.Thesp_detach_dbstoredprocedureisusedtodetachthedatabaseandcanrunUPDATESTATISTICSonalltablesbeforedetachingthedatabasewhilethesp_attach_dbstoredprocedureisusedtoattachthedatabaseinitsnewlocation.IncorrectAnswers:B:DTScanimportdatafromatextfileorfromanOLEDBdatasourcesuchasaMicrosoftAccess2000databaseintoSQLServer.ItcanalsoexportdatafromSQLServertoanOLEDBdatadestination.Itprovidesforhigh-speeddataloadingfromtextfilesintoSQLServertables.However,itisnotthefastestwaytomoveawholedatabasefromoneservertoanother.C:Beforeadatabasecanberestoredfromabackuptoanewlocation;thedatabasemustfirstberecreatedinthedestinationasthebackupholdsonlythedatafilesthatbelonginthevarioustables.Itdoesnotholdthetabledefinitions.Thisisnotthefastestmethodtomoveadatabase.D:TheDISKINITandDISKREFITcommandscannotbeusedtomoveadatabasefromoneservertoanother.Note:DISKINITandDISKREINITarefeaturesthatareusedinaSQLServer6.x.inSQLServer6.x,DISKINITisusedtocreatedatabaseortransactionlogdevicestostorethespecifieddatabaseortransactionlogwhenDISKINITfollowedeitheraCREATEDATABASEorALTERDATABASEstatementwhileDISKREINITisusedtorestoredeviceentriestoappropriatesystemtableswhenthedeviceentrywasmissingfromsysdevices.InSQLServer2000theCREATEDATABASEandALTERDATABASEstatementsallowforthecreationofseparatedataandlogfiles.BothCREATEDATABASEandALTERDATABASEcreateoperatingsystemfilesanddatabasesinasinglestep.ItisthusrecommendedthatallreferencestoDISKINITshouldberemovedinSQLServer2000andreplacedwithreferencestoeitherCREATEDATABASEorALTERDATABASE.

第4题:

ompany.com has a Micro-Partitioned p5-570 4-way with six application partitions and two VIO servers. Each VIO server has been allocated 0.5 CPU and the application servers have been allocated 0.4 CPUs. The marketing department wants to deploy a new Web server to support the release of a product. The systems architect has recommended that the Web server will require a whole CPU. Which of the following should the technical specialist suggest to provide the most cost-effective deployment?()

  • A、Remove one application server partition and apply its CPU resources to the Web server.
  • B、Reassign the CPU from one of the VIO servers and create the new partition.
  • C、Add 0.6 CPU to one of the application servers and run the Web service with the application. 
  • D、Reassign a total of 0.4 CPUs from the application servers and create a new partition with awhole CPU for new deployment.

正确答案:D

第5题:

The database on a p5-570 Micro-Partition has grown and backups are not meeting the Service Level Agreement. There are several partitions using the Virtual I/O Server to access the storage array. The database backup has high CPU utilization while the others have low CPU utilization. What adjustment can the technical specialist make to ensure that the Service Level Agreement is achieved?()

  • A、Add memory to the database partition to improve response time.
  • B、Add additional Host Bus Adapters to the server to improve IO throughput.
  • C、Modify CPU allocations to favor the database partition.
  • D、Increase CPU allocations to the Virtual I/O Server.

正确答案:C

第6题:

A technical specialist has a requirement to implement a 4-way POWER5 server with a small Web server partition and a high performance database server partition. The Web server provides a client front-end to the database server. The most important concerns are speed of communication between the Web server and the database and I/O speed of the database. Which of the following virtualization features would be most appropriate?()

  • A、Virtual SCSI
  • B、Virtual Ethernet
  • C、Virtual I/O Server
  • D、Micro-Partitioning

正确答案:B

第7题:

The staff is not able to access a database server.  The server has an ’Operating System not found’error and is set to boot from a fiber channel SAN. All other database servers are set to boot from the SAN and access the same switch and data as this database server. Which of the following is the MOST likely cause of the problem?()

  • A、The SAN is offline
  • B、Fiber channel switch
  • C、Multiple failed drives in the SAN
  • D、HBA

正确答案:D

第8题:

You are the administrator of two Microsoft Windows 2000 advanced server computers. On these servers, you are configuring a database that will store accounting information for your company.

The data must be available at all times. Interruptions in data connectivity should not last longer than five minutes. Any changes to the database should not require you to reconfigure the client computers.

How should you configure the database?

A.Configure the database on the two servers as a SQL Server 2000 cluster.

B.Configure the database on one server, and then configure a standby database on the second server.

C.Configure the database on each server. Use Microsoft Distributed Transaction Coordinator to keep the two servers perfectly synchronized.

D.Configure the database as a federated database, and then partition half the data on each server.


正确答案:A
解析:Explanation: SQL Server 2000 failover clustering provides high availability support by allowing us to configure one failover cluster to automatically, with no manual configuration, fail over to any other node in the failover cluster configuration. In this way, we minimize system downtime and provide high server availability during an operating system failure or a planned upgrade. Before SQL Server 2000 failover clustering can be set up, we must install Windows NT 4.0, Enterprise Edition, Windows 2000 Advanced Server or Windows 2000 Datacenter Server, and the Microsoft Cluster Service (MSCS).

In this scenario a cluster would be preferred to a standby server because it would be available immediately. A standby server on the other would require manual configuration and more time to become online.

Incorrect Answers:
B: A standby server would require you to reconfigure clients to allow it to connect to the standby server when the main server goes down. It would require at least several minutes of manual administration before the standby server would be operational. But the scenario requires that no reconfiguration of the client computers should be necessary. Therefore we should use a SQL Server 2000 cluster not a standby server.

Note: A standby server is a second server that contains a copy of the databases on the primary server and that can be brought online in the event of a primary server failure or due to scheduled maintenance on the primary server. This allows users to continue working with databases when the primary server becomes unavailable. When the primary server becomes available again, any changes to the standby server's copies of databases must be restored back to the primary server.

C: The Microsoft Distributed Transaction Coordinator coordinates distributed transactions, but would not increase availability.

Note: The Microsoft Distributed Transaction Coordinator (MS DTC) is a transaction manager that allows client applications to include several different sources of data in one transaction. MS DTC coordinates committing the distributed transaction across all the servers enlisted in the transaction.

An installation of SQL Server 2000 can participate in a distributed transaction by calling stored procedures on remote servers running SQL Server, automatically or explicitly promoting the local transaction to a distributed transaction and enlist remote servers in the transaction, and making distributed updates that update data on multiple OLE DB data sources. If these OLE DB data sources support the OLE DB distributed transaction interface, SQL Server 2000 can also enlist them in the distributed transaction. The MS DTC service coordinates the proper completion of the distributed transaction to ensure that either all of the updates on all the servers are made permanent, or, in the case of errors, all erased.

D: With Federated SQL Server 2000 servers, SQL Server 2000 databases can be spread across a group of autonomous database servers. These are capable of supporting the processing growth requirements of the largest Web sites and enterprise data-processing systems built with Microsoft Windows DNA, which divides the processing units of a data processing system into logical tiers. This however does not improve availability.

第9题:

The workload requirement for a Web server running in Micro-Partitioned p5-550 has increased 300 percent over the past six months. The initial partition definitions assigned 0.5 processing units and one virtual processor to the Web server partition. Three months previously, an additional 0.5 CPU was added to the Web server partition. When the technical specialist attempted to allocate a further 0.5 CPU to this partition, no additional performance was achieved. Which of the following actions would most likely resolve the problem?()

  • A、Add another virtual Ethernet.
  • B、Change the partition to be uncapped.
  • C、Change the number of virtual processors to 2.
  • D、Increase the amount of memory assigned to the partition by 300 percent.

正确答案:C

第10题:

Company.com has a database application and a Web server application running on the same p5-570 server in a single partition. Recently there have been a number of instances where the increased load on the database server has impacted the performance of the Web server. What can the technical specialist recommend to keep the database application from impacting the performance of the Web server?()

  • A、Create a VLAN between the web server and database server.
  • B、Purchase APV and install the VIOS.
  • C、Increase the priority of the Web server.
  • D、Create separate LPARs for Web and database workloads.

正确答案:D