Estimating schedule activity

题目

Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating. 空白(1)处填()

  • A、accuracy
  • B、approximation
  • C、specification
  • D、summary
参考答案和解析
正确答案:D
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.

A.estimating

B.defining

C.planning

D.sequencing


参考答案:D

第2题:

● On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and (70) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

A.time estimating

B.cost estimating

C.project planning

D.schedule development


正确答案:D

第3题:

Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.

A.activity duration estimating, schedule developing, activity resource estimating

B.activity resource estimating, activity duration estimating, schedule development

C.schedule developing, activity resource estimating, activity duration estimating

D.activity resource estimating, schedule developing, activity duration estimating


参考答案:B

第4题:

● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.

(71)

A.activity duration estimating, schedule developing, activity resource estimating

B . activity resource estimating, activity duration estimating, schedule development

C.schedule developing, activity resource estimating, activity duration estimating

D.activity resource estimating, schedule developing, activity duration estimating


正确答案:B
试题(71)分析
 项目时间管理包括使项目按时完成所必需的管理过程。进度安排的准确程度可能比成本估计的准确程度更重要。考虑进度安排时要把人员的工作量与花费的时间联系起来,合理分配工作量,利用进度安排的有效分析方法来严格监视项目的进展情况,以使得项目的进度不致被拖延。
 项目时间管理过程包括:活动定义、活动排序、活动的资源估算、活动历史估算、制定进度计划及进度控制六个步骤。
 以上六个步骤具有先后顺序,因此选择“活动的资源估算”activity resource estimating、“活动历史估算”activity duration estimating、制定进度计划schedule                 development,所以选B。
参考答案
(71)B

第5题:

● Estimating activity durations uses information on activity scope of (74),required resource types, estimated resource quantities, and resource calendars.

(74)

A. milestone

B. baseline

C. quality

D. work


正确答案:D


 

 

第6题:

● (73) is one of the techniques used for estimating activity durations.

(73)

A.Analogous Estimating

B.Precedence Diagramming Method (PDM)

C.Dependency Determination

D.Schedule network Templates


正确答案:A
试题(73)分析
    下列用于活动历时估算的技术是答案A类比估算法。
参考答案
    (73)A

第7题:

Estimating activity durations uses information on activity scope of(74) , required resource types, estimated resource quantities, and resource calendars.

A.milestone

B.baseline

C.quality

D.work


正确答案:D
解析:估算活动历时使用的信息包括活动的工作范围、所需资源类型、估算的资源数量,以及资源日历。

第8题:

The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.

A.estimating

B.defining

C.planning

D.sequencing


参考答案:A

该题的关键词为"schedule activity durations",其语句结构为"The process(主语)of()schedule activity durations uses(谓语)information",语句的含义为"(?)进度活动持续时间的过程使用信息",结合选项,此处应该选择动词,所以观察对进度活动持续时间采取什么行为会应用到各种信息(information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities),只有在估算进度活动持续时间时才会使用这些信息得到活动的工期,其他选项容易排除,因而选项A符合题意要求。

第9题:

Estimate activity durations is the processof estimating the number of work periods to complete indivities with estimatedresources . the tools and technques is not including().

A.expert judgment

B.analogous estimating

C.requiremen tstraceability matrix

D.three-point estimating


正确答案:C

第10题:

______is one of the techniques used for estimating activity durations.

A.Analogous Estimating

B.Precedence Diagramming Method(PDM)

C.Dependency Determination

D.Schedule network Templates


正确答案:A
解析:下列用于活动历时估算的技术是答案A类比估算法。

更多相关问题