The() defines the phases that connect the beginning of a project to its end.
第1题:
Project life cycles provide a better means of measurement of progress and control. The four phases of a project are conceptual development, _____, _____, and _____.
APreliminary planning, detail planning, closeout
BImplementation, reporting, termination
CDevelopment, implementation, termination
DExecution, reporting, finishing
EImplementation, termination, post-audit review
第2题:
A negative cost variance and positive schedule variance means:
A The project is under budget and ahead of schedule
B The project is over budget and behind schedule
C The project is over budget and ahead of schedule
D The project will be overrun but ahead of schedule at completion
第3题:
The extent of project management techniques to be used on a project are determined mainly by the _____ and _____ of the project.
A . budget, schedule
B . quality requirements, schedule
C . size, type of industry
D . nature, size
E . project manager, sponsor
第4题:
● The time necessary to complete a project is called the _______ of a project.
A Implementation Time
B Life Cycle
C Operation Time
D Critical Path
E Completion Phase
第5题:
66 The time necessary to complete a project is called the _______ of a project.
A. Implementation Time
B. Life Cycle
C. Operation Time
D. Critical Path
E. Completion Phase
第6题:
The sequential steps that define the process for successfully completing a project is:
A.Implementation Plan
B.a life cycle
C.Development Plan
D.a critical path
E.Management Plan
第7题:
115 The sequential steps that define the process for successfully completing a project is: A. Implementation Plan
B. a life cycle
C. Development Plan
D. a critical path
E. Management Plan
第8题:
The time necessary to complete a project is called the _______ of a project.
A.Implementation Time
B.Life Cycle
C.Operation Time
D.Critical Path
E.Completion Phase
第9题:
69 The extent of project management techniques to be used on a project are determined mainly by the _____ and _____ of the project.
A. budget, schedule
B. quality requirements, schedule
C. size, type of industry
D. nature, size
E. project manager, sponsor
第10题:
● Project life cycles provide a better means of measurement of progress and control. The four phases of a project are conceptual development, _____, _____, and _____.
A Preliminary planning, detail planning, closeout
B Implementation, reporting, termination
C Development, implementation, termination
D Execution, reporting, finishing
E Implementation, termination, post-audit review