第1题:
92 Project life cycles provide a better means of measurement of progress and control. The four phases of a project are conceptual development, _____, _____, and _____.
A. Preliminary planning, detail planning, closeout
B. Implementation, reporting, termination
C. Development, implementation, termination
D. Execution, reporting, finishing
E. Implementation, termination, post-audit review
第2题:
67 Life Cycle Costing:
A. is the concept of including all costs within the total life of a project.
B. is an activity devoted to optimizing cost/performance
C. is an activity of appraising the cost and technical performance of a completed project.
D. is a process of predicting the life of a project.
E. None of the above.
第3题:
Project life cycles provide a better means of measurement of progress and control. The four phases of a project are conceptual development, _____, _____, and _____.
APreliminary planning, detail planning, closeout
BImplementation, reporting, termination
CDevelopment, implementation, termination
DExecution, reporting, finishing
EImplementation, termination, post-audit review
第4题:
● The project life-cycle can be described as(72).
(72)
A.project concept, project planning, project execution, and project close-out
B.project planning, work authorization, and project reporting
C.project planning, project control, project definition, WBS development, and project termination
D.project concept, project execution, and project reporting
第5题:
● Which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?
A 5%
B 10%
C 15%
D 25%
E 50%
第6题:
185 Life Cycle Costing:
A. is the concept of including all costs within the total life of a project.
B. is an activity devoted to optimizing cost/performance
C. is an activity of appraising the cost and technical performance of a completed project.
D. is a process of predicting the life of a project.
E. None of the above
第7题:
● Project life cycles provide a better means of measurement of progress and control. The four phases of a project are conceptual development, _____, _____, and _____.
A Preliminary planning, detail planning, closeout
B Implementation, reporting, termination
C Development, implementation, termination
D Execution, reporting, finishing
E Implementation, termination, post-audit review
第8题:
During which phase of the project life cycle is the amount at stake lowest?
A concept
B development
C execution
D conclusion
E C and D
第9题:
● A project life cycle is a collection of generally sequential project (73)whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic (74)for managing the project, regardless of the specific work involved.
(73)
A. phases
B. processes
C. segments
D. pieces
(74)
A. plan
B. fraction
C. main
D. framework
第10题:
The(67)defines the phases that connect the beginning of a project to its end.
A.schedule
B.project life cycle
C.temporary
D.milestone