() is one of the quality planning outputs.
第1题:
87 The key ingredient to a successful quality management program are _____.
A. management's quality philosophy, operational quality assurance and operational quality control. B. quality evaluation methods and functional quality integrators.
C. technical quality administration, the technical quality specifications, and the quality process review. D. quality evaluation methods, quality progress reviews and the technical quality specifications.
E. All of the above
第2题:
● Project(71)is an uncertain event or condition that, if it occurs, has a positive or a negative effect on at least one project objective, such as time, cost, scope, or quality.
(71)
A.risk
B.problem
C.result
D.data
第3题:
The key ingredient to a successful quality management program are _____.
A . management's quality philosophy, operational quality assurance and operational quality control.
B . quality evaluation methods and functional quality integrators.
C . technical quality administration, the technical quality specifications, and the quality process review.
D . quality evaluation methods, quality progress reviews and the technical quality specifications.
E . All of the above.
第4题:
Project ______is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.
A.risk
B.problem
C.result
D.data
第5题:
According to the principles or the six key points proposed by Harvard Business School to judge the quality of an elevator pitch, it may be inferred that the example given in lesson five could be a defective one.()
第6题:
Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.
A.Benchmarking
B.Quality metric
C.Quality checklist
D.Brainstornung
第7题:
● (75)is one of the quality planning outputs.
(75)
A. Scope base line
B. Cost of quality
C. Product specification
D. Quality checklist
第8题:
● The project team members should also be aware of one of the fundamental tenets of modern quality management: quality is planned ,designed and built in, not (72 ).
(72)
A. executed in
B. inspected in
C. check-in
D. look-in
第9题:
●Quality planning tools are often used to help plan effective quality management activities.(71) is one of such tools, which involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance.
(71)A. Benchmarking
B. Quality metric
C. Quality checklist
D. Brainstorming
第10题:
is one of the quality planning outputs.
A.Scope base line
B.Cost of quality
C.Product specification
D.Quality checklist