第1题:
Project management has been proven to be successful because employees get to see the entire effort, from beginning to end, rather than just small pieces. This could be considered an example of:
A Behavioral modification
B Linking performance to pay
C Positive job reinforcement
D Job enrichment
E All of the above
第2题:
137 Project management has been proven to be successful because employees get to see the entire effort, from beginning to end, rather than just small pieces. This could be considered an example of: A. Behavioral modification
B. Linking performance to pay
C. Positive job reinforcement
D. Job enrichment
E. All of the above
第3题:
A program is characterized as:
A.a grouping or related tasks lasting one year or less.
B.a unique undertaking having a definite time period.
C.a grouping of similar projects having no definite end that supports the product(s) from cradle to grave.
D.a project with a cost over $ million.
E.None of the above.
第4题:
● The use of the project reports:
A are not necessary on small projects
B provides a means whereby various levels of authority can judge project performance
C provides insight into project areas and the effectiveness of the control systems
D All of the above
E B and C
第5题:
200 A program is characterized as:
A. a grouping or related tasks lasting one year or less.
B. a unique undertaking having a definite time period.
C. a grouping of similar projects having no definite end that supports the product(s) from cradle to grave. D. a project with a cost over $1 million.
E. None of the above
第6题:
A negative cost variance and positive schedule variance means:
A The project is under budget and ahead of schedule
B The project is over budget and behind schedule
C The project is over budget and ahead of schedule
D The project will be overrun but ahead of schedule at completion
第7题:
171 Documented work authorization provide:
A. a means of effective internal coordination of the project's activities.
B. an audit trail of all work authorized from project initiation to completion
C.a means for communication of work activity between the project manager and the performing activities.
D. All of the above
E. A and B only
第8题:
Documented work authorization provide:
A.a means of effective internal coordination of the project's activities.
B.an audit trail of all work authorized from project initiation to completion.
C.a means for communication of work activity between the project manager and the performing activities.
D.All of the above
E.A and B only.
第9题:
96 A negative cost variance and positive schedule variance means:
A. The project is under budget and ahead of schedule
B. The project is over budget and behind schedule
C. The project is over budget and ahead of schedule
D. The project will be overrun but ahead of schedule at completion
第10题:
means that every project has a definite beginning and a definite end.
A.Project phase
B.Unique
C.Temporary
D.Closure