When you create a network implementation VLAN solution, what

题目
单选题
When you create a network implementation VLAN solution, what is one procedure that you should include in your plan?()
A

Perform an incremental implementation of components.

B

Following the PPDIOO model, implement the entire solution and then test end-to-end to make sure that it is performing as designed.

C

Implement trunking of all VLANs to ensure that traffic is crossing the network as needed before performing any pruning of VLANs.

D

Test the solution on a segmented portion of a lab network prior to rolling out across the entire network.

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

You have a computer that runs Windows Vista. You create a virtual private network (VPN) connection between the computer and your company’s network.You notice that while the computer is connected through the VPN connection, users on the company network can access shared folders on the computer.You need to prevent network users from accessing your shared folders when you are connected to the company’s network by using the VPN connection.What should you do?()

A.A

B.B

C.C

D.D


参考答案:C

第2题:

What is an important step to take when verifying a newly proposed network security solution? ()

  • A、Test the design on a pilot network for expected results prior to implementing on the production network.
  • B、Run a network audit to determine types of traffic in use on the network.
  • C、Launch campus updates into the production network and monitor impact to see if configuration changes are needed.
  • D、Create an interruption of data flow to determine test "back-door" access methods.

正确答案:A

第3题:

Network access protection (NAP) is configured for the corporate network. Users connect to the corporate network by using portable computers. The command policy required confidentiality of data when is in transmit between the portable computers and the servers. You need to ensure that users can access network resources only from computers that comply with the company policy. What should you do?()

A.Create an Ipsec enforcement network policy.

B.Create an 802.1xenforcemen tnetwork policy.

C.Createa wired network(IEEE802.3)Group policy.

D.Create an extensible authentication protocol(EAP)enforcement network policy.


参考答案:A

第4题:

Which three of the following are organizational objectives that should be addressed when developing a new VLAN implementation plan? ()

  • A、network management
  • B、improving QoS
  • C、determining budget
  • D、reducing costs
  • E、increasing competitiveness
  • F、improving customer support

正确答案:D,E,F

第5题:

You have just created a new VLAN on your network.  What is one step that you should include in your VLAN-based implementation and verification plan? ()

  • A、Verify that trunked links are configured to allow the VLAN traffic.
  • B、Verify that the switch is configured to allow for trunking on the switch ports.
  • C、Verify that each switch port has the correct IP address space assigned to it for the new VLAN.
  • D、Verify that different native VLANs exist between two switches for security purposes.

正确答案:A

第6题:

Your network consists of a single Active Directory domain. All network servers run Windows Server 2003Service Pack 2 (SP2).A server hard disk drive fails. You replace and configure the hard disk drive and use Windows Backup to start a data restore.When you start the restore, you receive the following error message.You need to restore the data on the server. The solution must create the same directory structure that existed beforethe disk failure.What should you do? ()

A. Catalog the backup file.

B. Restore the backup to a single folder.

C. Restore the files to the original location.

D. Restore the backup to an alternate location.


参考答案:D

第7题:

What is a critical piece of information that you should have when creating a VLAN-based implementation plan?()

  • A、approval from senior management
  • B、end-user requirements
  • C、IEEE 802.1X authentication parameters
  • D、a summary implementation plan

正确答案:D

第8题:

In OOD what is the reason when you create a Sequence diagram?__


正确答案:
             

第9题:

What network information do you need when you plan to implement a VLAN-based solution?()

  • A、default VLAN information for all unused switch ports
  • B、802.1x configuration parameters 
  • C、number of IP subnets needed
  • D、IP routing protocol information

正确答案:C

第10题:

Which two are needed components when designing and implementing a security solution?()

  • A、detailed VLAN information
  • B、an incident response plan
  • C、results of testing the new network configuration
  • D、an existing hierarchical network topology
  • E、a security policy for your organization

正确答案:B,E

更多相关问题