项目立项表(Project Charter)中应当包含下述哪些内容:()

题目
多选题
项目立项表(Project Charter)中应当包含下述哪些内容:()
A

问题陈述

B

项目目标

C

项目团队组成与分工

D

初步拟订的改进方案

参考答案和解析
正确答案: D,B
解析: 暂无解析
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

The project charter is developed by:

A.senior management

B.the customer

C.the project manager

D.both A and C

E.None of the above.


正确答案:D
D

第2题:

10 The project charter is developed by:

A. senior management

B the customer

C. the project manager

D. both A and C

E. None of the above


正确答案:D

第3题:

The project charter is a document designed to tell _____ exactly what the project entails.

AThe project manager

BThe project office

CThe project team

DThe project sponsor

EAnyone associated with the project


正确答案:E

 

第4题:

● The project charter is developed by:

A senior management

B the customer

C the project manager

D both A and C

E None of the above.


正确答案:D

第5题:

139 The project charter is a document designed to tell _____ exactly what the project entails.

A. The project manager

B. The project office

C. The project team

D. The project sponsor

E. Anyone associated with the project


正确答案:E

第6题:

The identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives are indentified in the _____ phase of the project but first documented in the project _____.

A.Conceptual, charter/baseline.

B.Conceptual, master schedule.

C.Development, charter/baseline.

D.Development, master schedule.

E.Development, masterplan.


正确答案:A
A

第7题:

123 The scope baseline/project charter is prepared by the:

A. Project manager

B. Project manager and project office

C. Project manager, project office and functional team

D. Project manager, project office, functional team and project sponsor

E. Project manager, project sponsor and customer/user


正确答案:E

第8题:

The scope baseline/project charter is prepared by the:

AProject manager

BProject manager and project office

CProject manager, project office and functional team

DProject manager, project office, functional team and project sponsor

EProject manager, project sponsor and customer/user


正确答案:E
E

第9题:

● The scope baseline/project charter is prepared by the:

A Project manager

B Project manager and project office

C Project manager, project office and functional team

D Project manager, project office, functional team and project sponsor

E Project manager, project sponsor and customer/user


正确答案:E

第10题:

● The project charter:

A Expresses upper management commitment to the project.

B Provides that authority by which the project will be run.

C Establishes that organizational structure with the project.

D Specifies overall objectives and timeframe. of the project.

E All of the above.


正确答案:E

更多相关问题