第1题:
Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.
A.Project
B.project management team
C.performingorganization
D.customer
该题的关键词为"determine quality policies,objectives and responsibilities",其语句结构为"Project Quality Management processes(主语)include(谓语)all the activities of the (宾语)that determine quality policies,objectives and responsibilities(定语从句)",含义为"项目质量管理过程包括决定质量政策、质量目标以及质量责任的什么的所有活动",根据项目质量管理知识,只有组织才可以决定项目的质量政策,因而此处选择选项C。
第2题:
A.Management by objectives (MBO)
B.Participative management
C.Operational Management
D.Instructional Management
第3题:
Management By Objectives assumes that the team:
A is receptive to an unstructured environment.
B does not require close supervision.
C possesses a self directed philosophy
D identifies with project objectives.
E All of the above.
第4题:
______ is not among the Safety management objectives of the Company.
A.to provide for safe practices in ship operation and a safe working environment
B.to establish safeguards against all identified risks
C.to continuously improve safety management skills of personnel ashore and aboard ships,including preparing for emergencies related both to safety and environmental protection
D.to avoid damage to the environment,in particular,to the marine environment,and to property
第5题:
Human resource management is the management of human resources.It is function in organizations designed to maximize employee ( ) in service of an employer's strategic objectives.
A.work
B.job
C.scope
D.performance
第6题:
157 Management By Objectives assumes that the team:
A. is receptive to an unstructured environment.
B. does not require close supervision.
C. possesses a self directed philosophy
D. identifies with project objectives.
E. All of the above
第7题:
The objectives of the ISM Code are to ensure ①safety at sea②prevention of human injury or loss of life③avoidance of damage to the marine environment and to property
A.①
B.②
C.②③
D.①②③
第8题:
75 Management By Objectives assumes that the team:
A. is receptive to an unstructured environment.
B. does not require close supervision.
C. possesses a self directed philosophy
D. identifies with project objectives.
E. All of the above.
第9题:
Safety-management objectives of the Company should establish safeguards ______all identified risks.
A.with
B.without
C.against
D.above
第10题:
A safety shackle is identified by its ______.
A.Shape
B.Pin
C.Certification stamp
D.Color code