Configure the application monitor with a restart count of 0
Configure the application monitor with a monitor mode of Notify
Configure the application monitor with a notify method of Monitor
Configure the application monitor with a failure action of Notify
第1题:
Company.com has a six-node concurrent resource group with an application that is accessed by a web connection to the cluster nodes. How is the workload moved to another cluster node during a node failure?()
第2题:
An administrator has integrated a new application into an existing resource group. An application server withstart and stop scripts was defined and added to the resource group definition. The cluster was thensynchronized. How can the new application be started with minimal downtime?()
第3题:
A cluster administrator decides ti implement application monitoring in order to monitor both a web application and its supporting database. The plan is to use a single resource group prod_rg and to configure one monitor method for the web app and one monitor method for the database. Which of the following statements best describes the need for custom resource monitor?()
第4题:
What is a prerequisite for using the application availability analysis tool in HACMP?()
第5题:
To enhance the availability of an application running under HACMP, a decision was made to use The application monitoring facility. The application consists of several components and can take several minutes to initialize. The components use socket communication and can be initialized in any order as long as it is a serial order. The customer’s concern is that if the application stop and start scripts are used during application monitoring recovery,it may take an extraordinary length of time to reset all of the application components. What can be done to ensure the best recover time?()
第6题:
An administrator uses C-SPOC to change the user password for all nodes that belong to a Resource group. The administrator must perform this operation on a node that is:()
第7题:
During initial cluster planning session, a requirement is mandated that application monitoring will Be used to monitor the production database and three application servers. Since all the application servers rely on the database being active, only one resource group has been planned to manage the starting/stopping of the cluster resources. How ill the initial design impact the use of application monitoring?()
第8题:
An administrator is configuring an application monitor. Upon encountering an unrecoverable error the administrator does not want the resource group to failover. How can the application monitor be configured toachieve this?()
第9题:
An administrator is evaluating an application for application monitoring. What command should be Used to determine if the application can be monitored with a process monitor?()
第10题:
A network administrator receives complaints from the engineering group that an application on one server is not working properly. After further investigation, the administrator determines that source NAT translation is using a different source address after a random number of flows. Which two actions can the administrator take to force the server to use one address?() (Choose two.)