The features and functions that characterize a product,service,or result in a project are called( )
A.statement of workB.product scopeC.product qualityD.project scope
第1题:
91 The Risk of NOT meeting project quality objectives:
A. can be minimized through continuous monitoring.
B. considered a long term risk.
C. will be reflected in the "in-service" life of the product or service.
D. B and C
E. All of the above
第2题:
173 The Risk of NOT meeting project quality objectives:
A. can be minimized through continuous monitoring.
B. considered a long term risk.
C. will be reflected in the "in-service" life of the product or service.
D. B and C
E. All of the above.
第3题:
The Risk of NOT meeting project quality objectives:
A . can be minimized through continuous monitoring.
B . considered a long term risk.
C . will be reflected in the "in-service" life of the product or service.
D . B and C
E . All of the above.
第4题:
Project Quality Management must address the management of the project and the ()of the project.While Project Quality Management applies to all projects, regardless of the nature of their product,product quality measures and techniques are specific to the particular type of product produced by the project.()A.performance B.process C.product D.object
项目质量管理必需专注于对项目和项目产品的管理。当所有的项目在运用项目质量管理时,无论项目产品的本质如何,都要依据项目所产生产品的类型明确产品质量的度量和技术。
第5题:
● Project Quality Management must address the management of the projecand the (72) of the project. While Project Quality Management applies to alprojects, regardless of the nature of their product, product quality measureand techniques are specific to the particular type of product produced by thproject.
A.performance
B.process
C.product
D.object
第6题:
53 The Quality Risk _____ .
A. is minimized through continuous monitoring.
B. is considered a long term risk.
C. will be reflected in the in-service life of the project result.
D. B and C
E. All of the above
第7题:
A.project scope statement
B.project requirement
C.project charter
D.product specification
第8题:
The Quality Risk _____ .
A is minimized through continuous monitoring.
B is considered a long term risk.
C will be reflected in the in-service life of the project result.
D B and C
E All of the above.
第9题:
●(74) describes, in detail, the project' s deliverables and the work required to create those deliverables.
(74) A. Product scope description
B. Project objectives
C. Product specification
D. The project scope statement
第10题:
()is the process of formalizing acceptance of the completed project deliverables. The key benefit of this process is that it brings objectivity to the acceptance process and increases the probability of final product, service,or result acceptance by validating each deliverable。
A、Validate scope
B、Define scope
C、Control scope
D、Collect requirement