Establishing a project(74)involves listen mile stones,activities,and deliverables with intend start and finish dates of which the scheduling of employees may be an element.

题目
Establishing a project(74)involves listen mile stones,activities,and deliverables with intend start and finish dates of which the scheduling of employees may be an element.

A.cost management plan
B.risk management
C.scope management plan
D.management schedule
参考答案和解析
答案:D
解析:
翻译:建立项目进度管理计划涉及里程碑,活动和可交付成果的开始和完成日期,人力资源日历也属于其中一种元素。A、成本管理计划 B、风险管理计划C、范围管理计划 D、进度管理计划
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

● Which of the following is indicative of negative float?

A The late start date is earlier than the early start date.

B The critical path supports the imposed end date.

C The early finish date is equal to the late finish date.

D When leads are employed in the schedule.

E The project is sinking.


正确答案:A

第2题:

Define Activities is the process of identifying the specific actions to be performed to produce the (71).

A.project elements

B.work drafts

C.work package

D.project deliverables


正确答案:D
解析:活动定义过程识别是为了生产项目的可交付物而必须执行的具体活动。

第3题:

Which of the following is indicative of negative float?

A.The late start date is earlier than the early start date.

B.The critical path supports the imposed end date.

C.The early finish date is equal to the late finish date.

D.When leads are employed in the schedule.

E.The project is sinking.


正确答案:A
A

第4题:

●Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to (75) progress.

(75)

A. analyze

B. track

C. level

D. extend


正确答案:B

第5题:

Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to(75) progress.

A.analyze

B.track

C.level

D.extend


正确答案:B
解析:通常,制订项目进度计划是一个反复迭代的过程,该过程确定每个活动和每个里程碑的开工日期和完成日期。制订进度过程要求对历时估算和资源估算进行评审和修订,从而产生一个经过认可的项目进度表,作为对项目进展进行追踪的基准。

第6题:

● Free float is the amount of time that an activity may be delayed with out affecting the _____.

A Early start of the succeeding activities.

B Late start of the succeeding activities.

C Project finish.

D Cost of the project.

E None of the above.


正确答案:A

第7题:

Project work packages are typically decomposed into smaller components called activities to provide a basis for (72) ,scheduling, executing, and monitoring and controlling the project work.

A.reviewing

B.estimating

C.auditing

D.expecting


正确答案:B
解析:把项目工作包分解成更小的结构称为活动的单元,为估算、进度安排、项目执行、项目监控提供了基础。

第8题:

Free float is the amount of time that an activity may be delayed with out affecting the _____.

A.Early start of the succeeding activities.

B.Late start of the succeeding activities.

C.Project finish.

D.Cost of the project.

E.None of the above.


正确答案:A
A

第9题:

● Define Activities is the process of identifying the specific actions tobe performed to produce the (71).

(71)

A. project elements

B. work drafts

C. work package

D. project deliverables


正确答案:D

第10题:

●(74) describes, in detail, the project' s deliverables and the work required to create those deliverables.

(74) A. Product scope description

B. Project objectives

C. Product specification

D. The project scope statement


正确答案:D