When the i5/OS partition is housed in the p5 590, the HMC allows seamless installation in a partition as long as the minimum one processor, 256 MB of memory, one Ethernet and one boot adapter/disk is available from internal hardware.
V5R3 and later releases of i5/OS can be installed on a POWER5 server partition. Only one processor can be assigned to the i5/OS. A special expansion tower must be ordered. This expansion tower and its devices can be shared with other OS partitions.
When the i5/OS partition is housed in the p5 590, the 5250 Twinaxial console must be used to set up the partition. Only one processor can be assigned to the i5/OS partition. A special expansion tower must be ordered to house the IOPs. Devices in the special expansion tower can be shared with other Linux partitions.
V5R3 and later releases of i5/OS can be installed on IBM eServer p5 servers. i5/OS can run on two processors in the p5 590. A special expansion tower must be ordered. This expansion tower and its devices cannot be shared with other OS partitions. The iSeries expansion towers are seen by the IBM eServer p5 server as an I/O subsystem.
第1题:
Companycom wants to reduce the number of copper, Ethernet adapters on their 4 way p5 570 running AIX 5.3 used in each of the four LPARs. Companycom has one database LPAR, two application LPARs, and one web LPAR. Only the Web LPAR needs to communicate with the outside world. What is the minimum number of Ethernet adapters that should be provided to ensure redundancy and no single point of failure?()
第2题:
One of the key decision making factors in a very competitive opportunity will be cost. Companycom needs an aggregate rPerf rating of 120. What is the best solution?()
第3题:
A customer wants to run eight production partitions each with the following: ? 0.7 CPU 1.65-GHz ? 4GB of RAM ? 2 Ethernet adapters They do not have room for many RIO drawers since rack space is currently scarce in their data center. They have significant unused SAN attached disk. In addition to the Advanced POWER Virtualization feature, which of the following is the minimum recommended configuration needed to meet the customer’s requirements?()
第4题:
Companycom has purchased a p5 590 with 16 CPUs. To run Simultaneous Multi-Threading (SMT) with a 4-way virtual processor partition with 2.0 processing units of entitlement, how many logical CPUs will be allocated?()
第5题:
A customer has an entry level Power System that is currently partitioned and managed by a Hardware Management Console (HMC). For operational reasons, it must be disconnected from the HMC and configured as a new development system. How should the customer proceed to implement PowerVM Express and Integrated Virtualization Manager (IVM) on this Power System? ()
第6题:
Companycom wants to know how to keep track of the latest level of microcode for their p5 systems to stay current. What is the best way to monitor for new microcode?()
第7题:
Companycom has just purchased a p5 570 with AIX 5.3. The customer would like to add a training LPAR to the system, but no processors are available. All of the partitions are using dedicated resources. The test LPAR is using one processor and has a 90% CPU idle rate. What can be done to setup this training LPAR quickly without disabling their current environment?()
第8题:
Companycom has a 16 way 1.65 GHz p5 590 and wants to install a i5/OS partition on their server. The customer wants to keep installation costs to a minimum by sharing devices between all LPARs. Before the operating system can be installed in this partition, the customer was told that there are certain limitations that must be observed. What are these limitations?()
第9题:
Companycom is installing a p5 590 with a HMC to manage LPARs. The customer is very concerned about security and wants to restrict network traffic that is not necessary. What is necessary for communication between the LPARs and the HMC?()
第10题:
Companycom is currently using a p690 and has just ordered a p5 590. They prefer to run in full system partition mode, since their application will utilize all the resources in the machine, and they don't want the overhead of an LPAR. What is the best response to the customer about the POWER5 capabilities?()